Test Your Building Design on FIRSTVISION

Enabling FIRSTVISION to Monitor Your Building

3.9 Test Your Building Design on FIRSTVISION

It is recommended that you simulate an event that FIRSTVISION processes that will test the interaction between your building design and FIRSTVISION response to that event. The following are some items to verify that they are functioning correctly:

Battery-backup system is functioning correctly.

FIRSTVISION starts monitoring your building life safety system when started.

The floor plan background images are correctly displayed on FIRSTVISION.

Auto unlock of FIRSTVISION enclosure when an event that FIRSTVISION processes is received by FIRSTVISION.

Activated device icons are shown in their correct locations over the floor plan background on FIRSTVISION.

3.10Touch Screen Calibration

FIRSTVISION’s touch screen was calibrated in the factory and you should not have to perform this procedure.

If you have determined that the cursor is not correctly tracking to the position of your finger then you can use the GenCalb function to calibrate the touch screen.

3.10.1 How to Calibrate FIRSTVISION’s Touch Screen

Step 1. Unlock and open the product’s glass paneled door using the factory supplied key.

Step 2. Connect the external keyboard and mouse to the product to the appropriate connectors. Refer to “What To Connect and How To Make the Connections” on page 15.

Step 3. Press the ESC key on the keyboard to shutdown the software application. Step 4. Locate and click on the Desktop icon for touchscreen calibration.

Step 5. Follow the displayed instructions to calibrate the touch screen.

Step 6. Restart the software application by clicking on FIRSTVISION’s software application Desktop shortcut.

Step 7. Remove the external connected components.

FIRSTVISIONInstallation and Operation Manual - P/N: 53034:Rev: A2 10/29/07

27