3 Wiring continued

A Power

 

B Communication

The power requirement range for the AirAlertTM96d controller is 24 Vdc, 500 mA. The system must be grounded to the power supply. A dedicated circuit breaker should be used. Use 14 AWG two conductor, stranded cable (Belden 5100UE or equivalent), up to 1,000 ft.

If the controller is sharing a power supply with multiple sensors on the network, care must be taken to observe voltage drops (line loss) on the power cable. Supply voltages less than 17 Vdc can render some network devices inoperable. Any supply voltage less than 17 Vdc requires the installation of an additional power supply at that point on the power cable.

Depending on total power consumption, avoid

 

 

powering more than 10 network devices with one

 

 

power supply. Additional power supplies and/or

 

 

decreased number of network devices may be

 

 

required to compensate for line loss. Contact

 

 

Honeywell Analytics for help with all power

 

 

requirements.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

RC

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Note: Terminal J27 must be grounded to

 

R

 

 

mechanical ground.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

J23

Figure 5. Power Wiring

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

EOL2

 

RC

EOL3

 

 

RC

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

R

 

 

 

 

R

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

In

 

Out

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

J22

 

 

 

 

 

 

 

 

 

J23

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

V+

V-

V+

V-

 

 

A1

B1

A2

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The communication cables have to be grounded using the shield terminal. Up to 32 network devices can be installed on each channel.

Use 24 AWG two conductor, twisted and shielded cable (Belden 9841 or equivalent) for the connection. The network can be up to 2,000 feet per channel. The length of a T-tap can be a maximum of 65 feet (20 m). A maximum of 130 feet (40 m) for all the T-taps must be respected.

The communication cables have to be grounded using the shield terminal. Use twisted and shielded cable #24/2 AWG (Belden 9841) for the connection.

Note: Channel 4 is the slave communication channel to retransmit the MODBUS signal to PLC. No sensor can be connected to this channel.

Figure 6. Communications Wiring

 

 

 

 

 

End-of-line

Power

EOL3

 

EOL4

 

EOL1

jumper position

 

 

 

RC

Fault

 

 

 

 

 

 

RC

 

 

 

R

 

 

 

 

RC

 

 

 

 

 

 

 

TX

 

R

 

 

 

 

 

 

 

 

 

 

 

 

 

R

 

 

 

 

 

 

 

 

 

RX

A1 B1 A2 B2 SHLD

J24

 

B3 A4 B4

 

SHLD A3

 

Channel 2

Channel 4

Channel 1

Channel 3

Previous

Communication Requirements:

24 AWG twisted pair, shielded (Belden 9841 or equivalent)

Network can be up to 2,000 feet per channel

Avoid “T-taps” if possible

Do not exceed 65 feet per T-tap

Do not exceen 130 feet total of all T-taps

End-of-line specification:

The E.O.L. jumper for channels 1-2-3-4 must alwaysbe in E.O.L. position

Next

Communication wire shield must be connected to shield terminal(s) of controller (J23-J24)

Channels 1-2-3: Modbus protocol — Communicates only with Modbus devices

Channel 4: Modbus output only — No sensor can be connected to Channel 4

Manning AirAlert-96d Gas Monitor 19073 AIRALERT96D 05/2006 Prelim REVC Copyright © 2006 Honeywell Analytics. All Rights Reserved.