B. Sequence of Operation
1. Startup Cycle
When power supply is turned on, "on" appears on CB display and HGV energizes. 30 sec. later, harvest cycle starts.
•If the "RESET" button is pressed during
2.Harvest Cycle
HGV continues. Comp and AMD energize. WV energizes as listed in table below.
| CB | Initial Harvest | Initial Harvest after Bin Control | Normal Harvest | |||
Note | after Power On | Initiated Restart | |||||
Setting |
|
| |||||
| All WT | WT>48°F (9°C) | WT≤48°F (9°C) | WT>48°F (9°C) | WT≤48°F (9°C) | ||
|
| ||||||
WV Delay | NA | 20 sec. | 0 sec. | 0 sec. | 20 sec. | 20 sec. | |
WV Time after | 10, 11 | 95 sec. | 10 sec. | 95 sec. | 30 sec. | 95 sec. | |
WV Delay |
|
| (CB Setting NA) |
|
|
| |
WV Time | NA | 10 sec. | 0 sec. | 10 sec. | 0 sec. | 10 sec. | |
when |
|
|
|
|
|
| |
ET≥41°F |
|
|
|
|
|
| |
(5°C) |
|
|
|
|
|
| |
(CB Setting 1) |
|
|
|
|
|
|
Note: ET temperature is recorded 30 seconds after PM energizes in the preceding freeze cycle. Water temperature correction value (CB Setting 13) is added to ET temperature and this is used as WT value.
If CBT≤81°F (27°C) (CB Setting 74) at beginning of harvest cycle, HGV repeatedly energizes 40
When ET reaches harvest cycle termination temperature (CB Setting 1) of 41°F (5°C) , HGV
3. Freeze Cycle
Comp and FM continue. WV energizes for total time of WV Time 1 and WV Time 2 listed in table below. PM energizes after PM delay listed in table below.
| CB | Initial Freeze | Initial Freeze after Bin Control | Normal Freeze | |
Note | after Power On | Initiated Restart | |||
Setting |
| ||||
| All WT | All WT | All WT | ||
|
| ||||
PD | 12 | 30 sec. × 2 | 30 sec. × 2 | 30 sec. | |
WV Time 1 |
|
|
|
| |
and PM Delay |
|
|
|
| |
PD | 15 | 22 sec. × 2 | 22 sec. × 2 | 22 sec. | |
WV Time 2 |
|
|
|
| |
FD | 12 | 60 sec. | 60 sec. | 60 sec. | |
WV Time 1 |
|
|
|
| |
and PM Delay |
|
|
|
| |
FD | 15 | 44 sec. | 44 sec. | 44 sec. | |
WV Time 2 |
|
|
|
|
9