Item | Description | Yes | No | N/A | Initial |
|
|
|
|
|
|
|
|
8. Clearances | Inspect the proposed installation site to confirm clearance |
|
|
|
|
|
| requirements for installation and serviceability per the HP |
|
|
|
|
|
| POD 20c specifications. Necessary clearances are |
|
|
|
|
|
| determined, in part, based on the specific installation plans |
|
|
|
|
|
| and infrastructure design. Location, orientation, and planned |
|
|
|
|
|
| utilization can affect the necessary clearances. Consider |
|
|
|
|
|
| future planning for the space around the installation site. |
|
|
|
|
|
9. Support | Evaluate the HP POD 20c installation site in relation to the |
|
|
|
|
|
infrastructure | planned support infrastructure location. Conduit lengths and |
|
|
|
|
|
location | the utility pathway design must be taken into consideration in |
|
|
|
|
|
| the planning stages. The proposed support infrastructure |
|
|
|
|
|
| design and the location of required utilities are discussed |
|
|
|
|
|
| with the customer's site engineering personnel to identify |
|
|
|
|
|
| elements that can impact the HP POD 20c installation site |
|
|
|
|
|
| decisions. |
|
|
|
|
|
10. Support | Evaluate the proposed installation site for the HP POD 20c |
|
|
|
|
|
infrastructure for | and the support infrastructure for access requirements. The |
|
|
|
|
|
access requirements | evaluation is based on the information provided by the |
|
|
|
|
|
| customer at the time of the site visit. In the absence of |
|
|
|
|
|
|
|
|
|
|
| |
| used as the basis for the evaluation. The delivery path is |
|
|
|
|
|
| visually examined and discussed with the customer's site |
|
|
|
|
|
| engineering personnel to identify obstacles to installation. |
|
|
|
|
|
11. Site engineering | Conduct interviews with the customer's site engineering |
|
|
|
|
|
interviews | personnel and site facilities personnel to gather information |
|
|
|
|
|
| related to the origin of the power source and network |
|
|
|
|
|
| services that are proposed for use with the HP POD 20c. HP |
|
|
|
|
|
| must visually inspect the proposed power protection |
|
|
|
|
|
| equipment. Means of delivery, connections, and pathways |
|
|
|
|
|
| are documented. |
|
|
|
|
|
12. Capacity of | Based on the review of |
|
|
|
|
|
electrical | documentation (such as |
|
|
|
|
|
infrastructure | examine equipment panels and monitoring system data, as |
|
|
|
|
|
| available. HP must determine whether adequate capacity |
|
|
|
|
|
| exists in the current electrical infrastructure to be used or if |
|
|
|
|
|
| additional study is required. Determine if the level of |
|
|
|
|
|
| redundancy that is required as stated by the site engineering |
|
|
|
|
|
| personnel can be provided by using the existing |
|
|
|
|
|
| infrastructure. This takes into consideration the proposed |
|
|
|
|
|
| installation site of the HP POD 20c, the potential HP POD |
|
|
|
|
|
| 20c payload, and the customer stated redundancy |
|
|
|
|
|
| requirement. Components can include generators, UPSs, |
|
|
|
|
|
| and switch gear. |
|
|
|
|
|
13. Chilled water | Determine the overall chilled water capacity, available flow |
|
|
|
|
|
infrastructure | rates, and supply/return temperature restrictions. Determine |
|
|
|
|
|
| if any site specific requirements mandate additional chilled |
|
|
|
|
|
| water equipment, such as heat exchangers or mixing |
|
|
|
|
|
| apparatus. Locate any existing or planned supply/return |
|
|
|
|
|
| headers. |
|
|
|
|
|
14. Access control | Conduct interviews with the customer site engineering |
|
|
|
|
|
| personnel to determine the level of access control that is |
|
|
|
|
|
| required for the HP POD 20c and its infrastructure. The |
|
|
|
|
|
| proposed installation site is assessed for suitability in relation |
|
|
|
|
|
| to the customer requirements. |
|
|
|
|
|
| Appendix A: HP site assessment 27 |