Item |
| Description | Initial |
|
|
|
|
2 |
| Verify that the chilled water supply temperature meets the minimum POD chilled water supply |
|
|
| temperature of 12°C (55°F). |
|
3 |
| Verify that a sufficient chilled water flow rate is available. |
|
4 |
| If necessary, verify that the |
|
|
| attained. |
|
Power Requirements |
| ||
|
|
| |
Item |
| Description | Initial |
|
|
|
|
1 |
| Verify that the short circuit analysis, arc flash, and circuit breaker coordination studies are |
|
|
| complete. Verify power work is completed according to the approved conduit routing |
|
|
| drawings that show the exact routes, plan view, sections, and elevations. |
|
2 |
| Verify that temporary site power for installation and construction is planned and available, if |
|
|
| applicable. |
|
3 |
| Verify that adequate site power exists per the HP POD 20c requirements. |
|
General |
|
| |
|
|
| |
Item |
| Description | Initial |
|
|
|
|
1 |
| Verify the utility connection to the HP POD 20c and any required metering equipment. |
|
2 |
| Verify the |
|
3 |
| Verify that the HP Project Team coordinates with other site construction activities. |
|
Power infrastructure installation
When determining the final location of the power connections, consider the following:
•Distance between the facility utilities and the location of the HP POD 20c
•Distance between possible UPS or generator locations and the HP POD 20c
•Requirements for routing electrical feeders (underground or overhead)
The facility power connection must be installed in compliance with local electrical codes and regulations. HP reference electrical installation design is based on a maximum distance of 15.2 m (50 ft) or a line of sight between the disconnect and the HP POD 20c.
Appendix B: Preparing for delivery 31