NOTE: The blower motor housing can be mounted using 4 holes from either the inlet side or the outlet side of the blower.

Outlet Side

AA

A Outlet SideAAInlet SideComplete Preparation

A

A. Mounting holes

Inlet Side

A Manual backgroundManual backgroundManual backgroundManual backgroundManual backgroundManual background

A

A. Mounting holes

1.Position the in-line blower motor housing in its mounting location and mark the 4 mounting hole locations.

2.Drill 4 mounting pilot holes using a ³⁄₁₆" (4.8 mm) drill bit.

3.Attach the in-line blower motor housing to the mounting location with 4 - 6 x 80 mm mounting screws and washers.

4.If it is removed, reinstall the blower motor assembly and secure it with the screws previously removed.

5.If it is removed, reattach the motor electrical plug to the connector on the blower motor assembly.

Complete Preparation

1.Determine and make all necessary cuts for the vent system.

IMPORTANT: When cutting or drilling into the floor, ceiling or wall, do not damage electrical wiring or other hidden utilities.

2.Determine the location where the ¹⁄₂" (1.3 cm) wiring conduit will be routed through the floor, ceiling or wall between the in- line blower and the downdraft vent.

3.Drill a 1¹⁄₄" (3.2 cm) hole at this location.

4.Locate the electrical terminal boxes in the in-line blower housing and downdraft vent. Remove the terminal box covers and set the covers and screws aside.

B

A

A. Electrical terminal box

B. Electrical knockout

5.Remove the electrical knockout from the in-line blower housing and downdraft vent to prepare for the installation of the UL listed or CSA approved ¹⁄₂" (1.3 cm) wiring conduit and conduit connector.

6.With the downdraft vent mounted, run the ¹⁄₂" (1.3 cm) wiring conduit between the in-line blower motor housing and the downdraft vent. Pull enough ¹⁄₂" (1.3 cm) wiring conduit to allow for easy connection to the terminal boxes in the in-line blower housing and downdraft vent.

7.Run the six 18 AWG wires through the ¹⁄₂" (1.3 cm) wiring conduit and conduit connectors and into the terminal boxes on the in-line blower housing and downdraft vent. Leave enough wire length in each terminal box to make the wiring connections.

8.Install the conduit connectors and conduit to the in-line blower housing and downdraft vent electrical terminal boxes.

9.Connect the vent system to the downdraft vent and in-line blower system and seal all joints with clamps.