4.Replace the Switch Panel on the POWER FEED™ 10A CONTROLLER with the blank panel included with the pendant box.
5.Connect the Switch Panel to the mating
6.Fasten the Switch Panel to the pendant box.
7.Connect the
8.The remote pendant is now ready to be used.
Interfacing to the Switch Panel Controls:
The Switch Panel circuits can be accessed on the screwless terminal strip. Easy access to these circuits enables the POWER FEED™ 10A CONTROLLER to interface with custom controls or PLC’s. These circuits must see a contact closure to function properly.
1.Remove all input power to the POWER FEED™ 10A CONTROLLER including any auxiliary power supplies.
2.Remove the fasteners from the Switch Panel and disconnect the Switch Panel from the wire harness. The Switch Panel should be stored in a secure
CAUTION
place in the event that it is needed in the future.
The Switch Panel should not be left in the POWER FEED™ 10A CONTROLLER if the switches are not connected. This could cause a safety concern due to the fact that the switches will not stop the welding sequence, etc.
3.Jumper the wire harness connector (J2) to the mat- ing
4.Replace the Switch Panel on the POWER FEED™ 10A CONTROLLER with the blank panel included with the pendant box.
5.Remove the wire duct cover to gain access to the leads on the right side of the terminal strip.
6.Remove the leads going to the Pendant
7.Remove one of the plug buttons located on the bot- tom of the POWER FEED™ 10A CONTROLLER control box and install some type of strain relief for the interfacing leads.
8.Connect the interfacing leads to the Switch Panel circuits on the terminal strip (see Wiring Diagram for terminal strip designations). The supply for START, STOP, and INCH UP comes from SWITCH GROUP #1 SUPPLY on block #39. The supply for TRAVEL AUTO, TRAVEL ON, FLUX FILL, and INCH DOWN comes from SWITCH GROUP #2 SUPPLY on block #43.
9.To activate any of the Switch Panel circuits, a con- tact closure must be established between the sup- ply and the particular circuit it is referenced to – for instance, to start the weld sequence, a contact clo- sure must be established momentarily between ter- minal strip blocks #39 (SUPPLY) and #40 (START). See FIGURE A.2.