3. Operation

3.2 Start-up

Prior to initial start-up, check the UPS voltage settings.

The frequency of the output voltage (50 or 60 Hz) is automatically set to that of the input source.

8

24

1.Close the upstream device (ON position) controlling the supply of AC power to the UPS.

2.Set the battery circuit breaker(s) 8 to ON.

The buzzer beeps three times.

If the supply frequency is different than the default value set on the UPS, the new value is set and the buzzer beeps 4 times.

3. Press the ON / OFF button 24 .

All the equipment connected to the UPS is now energised, however it takes another 30 seconds before the UPS is fully operational.

After this time, the equipment connected to the UPS is protected.

If LED 22 or 23 do not go ON or if one of LED 14 , 15 , 16 or 17 flash, there is a fault (see section 4.1). In order to detect any wiring errors, it is essential that the AC-power source be present at the first switch-on. Subsequently, the device may be switched-on without the presence of the AC-power source.

3.3Bargraph indications

LEDs 14 to 17 provide three different indications.

14

15

16

17

18

Page 20 - 51033211EN/AC

1.Remaining backup time in percent.

2.Percent load drawn by the protected equipment, when button 18 is pressed.

3.Operating faults (flashing LED and beeps):

14Overload.

15UPS fault.

16Battery fault.

17Excessive ambient temperature.

Page 20
Image 20
MGE UPS Systems 3000 VA, 2000 user manual Start-up, Bargraph indications