The progress of the redundancy check appears in the Background Activities tab. If you click the link of the displayed task being advanced, the current progress status appears. On the screen, you can pause or stop the task.
Click
You can see the Progress bar.
NOTES:
If you try to provide a logical drive not
Redundancy check is started on unsyncronized logical drive (event ID:1547).
After redundancy check is completed, be sure to see the event log to check whether one or more errors occur during the redundancy check. If a media error occurred, a message indicating the occurrence appears before the message showing that the redundancy check is completed without any problem.
If rebuild is done for a logical drive at a time when redundancy check of the logical drive is previously scheduled, the redundancy check is skipped.
While redundancy check is run to a logical drive, a time when another scheduled redundancy check is to be run to the logical drive may come. If so, the scheduled redundancy check is skipped.
If the power is off at a time when redundancy check is scheduled previously, the scheduled redundancy check is skipped.
-39 -