Figure 25 Hole & New Framing Members

10" (254mm)

10" (254mm)

 

 

CHIMNEY

 

HOLE

NEW

EXISTING CEILING

JOISTS

FRAMING

 

MEMBERS

 

CEILING

 

Figure 25 Hole & New Framing Members

If the area above the ceiling is NOT an attic, position and secure the ceiling firestop on the ceiling side of the previously cut and framed hole.

NOTE: There must be NO INSULATION or other combustibles inside the framed firestop opening.

C. Vent Termination

For Horizontal Terminations - To attach and secure the termination to the last section of horizontal vent refer to the Cinch Pipe and Termination Cap installation instructions.

Push on and snap lock as described at the beginning of the Installing Vent Components section.

The termination kit should pass through the wall firestops from the exterior of the building.

Adjust the termination cap to its final exterior position on the building and interlock the flue sections.

WARNING: THE TERMINATION CAP MUST BE

!POSITIONED SO THAT THE ARROW IS POINTING UP.

 

For trapezoidal cap termination kits:

 

• Using screws secure the cap to the exterior wall through

JOIST

the flanges in the cap.

 

!

WARNING: VENTING TERMINALS SHALL

 

NOT BE RECESSED INTO A WALL OR SID-

 

 

 

ING. VENT TERMINATION CLEARANCES MUST

 

BE FOLLOWED TO AVOID FIRE DANGER. SEE

CEILING

VENT TERMINATION MINIMUM CLEARANCES DI-

 

AGRAM ON FOLLOWING PAGE.

NAILS (4 REQUIRED)

 

 

CEILING FIRESTOP

 

 

Figure 26. Ceiling Firestop (Ceiling Side)

 

 

If the area above the ceiling IS an attic, position and secure the firestop on top of the previously framed hole.

NOTE: Keep insulation away from the vent pipe at least 1 inch (25mm).

 

NAILS (4 REQUIRED)

 

 

 

 

 

7 1/4"

 

 

 

(184mm)

 

RAFTER

Figure 28.

Trapezoid Termination Cap

CEILING

 

 

 

 

CEILING FIRESTOP

 

 

Figure 27.

Attic Firestop

 

 

26

Quadra-FireQV-PIER, QV-ST Series: HV-IPI2005-901 Rev. G • 2/06

Page 26
Image 26
Quadra-Fire QV-PIER, QV-ST owner manual Hole & New Framing Members