Quantum GAS-FIRED BOILERS Electrical Wiring, Gas Piping, A. Electric Power Supply

Models: GAS-FIRED BOILERS

1 68
Download 68 pages 29.18 Kb
Page 29
Image 29
FIGURE 12 GAS PIPING

The length of pipe or tubing should be measured from the gas meter or propane second stage regulator.

FIGURE 12 GAS PIPING

ELECTRICAL WIRING

WARNING

TURN OFF ELECTRICAL POWER AT FUSE BOX BEFORE MAKING ANY LINE

VOLTAGE CONNECTIONS. FOLLOW LOCAL ELECTRICAL CODES.

All electrical work must conform to local codes as well as the National Electrical Code, ANSI/ NFPA70, latest revision. In Canada, electrical wiring shall comply with the Canadian Electrical Codes, CSAC22.1 and .2

A. ELECTRIC POWER SUPPLY

Prior to making any line voltage connections, service switch at boiler should be in the off position and the power turned off at the fuse box

Run a separate 120 volt circuit from a sperate over current protection device in the electrical service entrance panel. This should be a 15 ampere circuit. A service switch has been pre-wired and located on the exterior boiler jacket. See Fig. 13 for diagram showing location of service switch junction box and power supply connection points. Connect black (hot) lead from the power supply