Regency U32-LP4 For P36D-1 / P36-4Only, For U32-4Only, Ground wire from kit, Heat Shield, Chain

Models: U32-NG4 U32-LP4

1 40
Download 40 pages 28.31 Kb
Page 16
Image 16
Ground

INSTALLATION

25)Connect the DC spark generator wires to the SIT Valve with the screw, which is provided in the kit.

26)Locate the ground lug.

For P36D-1 / P36-4 Only:

26a) By the receptical box, left of the unit.

For U32-4 Only:

26b) Located on the left side of the unit.

27)Connect one end of the supplied green ground wire to the lug with the nut and washer from the kit.

Ground

wire from

kit

28)Run the other end of the ground wire and DC spark generator wires through the bushing on the heat shield.

Heat Shield

29)Install the 1/2" bushing to the heat shield.

30)Plug the DC spark generator wires to the DC Sparker.

31)Connect the ground wire to the DC Sparker mounting bracket.

32)Install the supplied battery into the DC Sparker Box by opening the battery compartment.

Battery

Compartment

33)Mount the heat shield to the DC Sparker. Secure into place with the velcro, which is provided in the kit.

34)Find a location which is not too hot and is easy to reach for changing the battery. Note: It should be kept away from the

chain.

Chain

35)Tie up the loose wires with the wire clip.

36)Check for gas leaks.

37)Check inlet and outlet pressures.

38)Check operation of flame control.

39)Check for proper flame appearance and glow on logs.

NOTE: The battery in the DC Sparker Box will need to be replaced an- nually.

16

U32-4 FPI Direct Vent Gas Insert

Page 16
Image 16
Regency U32-LP4 For P36D-1 / P36-4Only, For U32-4Only, Ground wire from kit, Heat Shield, Battery Compartment, Chain