Installation

Installation

Lifting and Rigging

Lifting and Rigging WARNING

DAMAGE TO EQUIPMENT OR PERSONNEL

Do not remove tension rods until the EcoBreeze Frame is placed and secured on its supports.

Before lifting the EcoBreeze Frame, ensure the lifting equipment is adequately sized for the load.

Lift and rig the EcoBreeze Frame from the top four ISO corners only.

Move the EcoBreeze Frame directly from the truck to its permanent foundation. If the Frame must be placed elsewhere temporarily, it must be placed on a flat and level surface in order to avoid damage.

Check for overhead obstructions such as power cables.

Maintain a minimum safe distance while equipment is hoisted.

Control access of personnel at lift site.

Failure to follow these instructions can result in death, serious injury, or equipment damage.

EcoBreeze Frame. The EcoBreeze Frame is not equipped with forklift pockets. Lift and rig only from the four upper ISO corner blocks on each EcoBreeze Frame using a crane. Recommended horizontal sling angles are greater than 45 degrees. Lifting equipment must be rated for at least 18 144 kg (40,000 lb) for lifting a 12.2 m (40 ft) Frame, and at least 12 247 kg (27,000 lb) for a 6 m (20 ft) Frame.