3. A split ferrite filter must be clamped to DataNET copper wire and
fixed immediately to the outside of the unit; use part number
1173000-013 ferrite contained in the CE Installation Kit. This is
required to meet the Conducted Immunity requirement for CE/EMC
Heavy Industrial. All other CE/EMC Heavy Industrial requirements
are met without the use of a ferrite clamp.
4. Shielded Ethernet cable must be used for all Ethernet connections,
in and outside the GC, and coupled through the enclosure using a
shielded RJ-45 coupler; use part number 1183200-003 contained in
the CE Installation Kit. A mounting plate (part number 2020261-001)
is also available to accomplish this. If needed for Zone 1 installation,
part numbers 2017984-001 and 2017985-001 is available to maintain
purge. If a PG gland is used to make the 360-degree termination of
the Ethernet shield at the enclosure, the Installation Kit and other
parts are not required.
12 • Installation 2000592-001