AS1020S-8 User's Manual

Choosing a Setup Location

-Leave enough clearance in front of the rack to enable you to open the front door completely (~25 inches).

-Leave approximately 30 inches of clearance in the back of the rack to allow for suffi cient airfl ow and ease in servicing.

-This product is for installation only in a Restricted Access Location (dedicated equipment rooms, service closets, etc.).

!

Warnings and Precautions!

 

Rack Precautions

!

Ensure that the leveling jacks on the bottom of the rack are fully extended to the fl oor with the full weight of the rack resting on them.

In single rack installation, stabilizers should be attached to the rack.

In multiple rack installations, the racks should be coupled together.

Always make sure the rack is stable before extending a component from the rack.

You should extend only one component at a time - extending two or more simul- taneously may cause the rack to become unstable.

Server Precautions

Review the electrical and general safety precautions in Chapter 4.

Determine the placement of each component in the rack before you install the rails.

Install the heaviest server components on the bottom of the rack fi rst, and

then work up.

Use a regulating uninterruptible power supply (UPS) to protect the server from power surges, voltage spikes and to keep your system operating in case of a power failure.

Allow the hot plug SCSI drives and power supply units to cool before touching them.

Always keep the rack's front door and all panels and components on the servers closed when not servicing to maintain proper cooling.