Floor Installation

Vermont Castings VCBVTN/TP & VCPVTN/TP Room Heater

1/16"

(1.6mm)

RH102

Fig. 4 Wall anchor.

Floor Installation

1.The heater may only be installed on a noncombus- tible flat surface. Wall mounting screws may be used to keep heater from side movements.

2.Measure heater mounting screws location “X” as desired above floor. (Fig. 5)

3.Use enclosed “paper template” for proper distance between holes. Be sure template is level. It may be necessary to use plastic or lead anchors for plaster wall.

4.Drill holes at marked locations using 9/64” drill bit.

5.Leave screw head out from wall far enough to attach heater.

 

Screw Holes

 

X

 

Floor

 

RH107

Fig. 5

Optional wall mounting screw for floor installation.

6

 

Connect to Gas Supply

Before connecting the appliance, turn of all gas appli- ances. Close the main gas valve at the gas meter or Lp tank. Make certain there is good ventilation where the installation will be made. Installation should comply with all applicable building codes and ANSI Z223.1, latest edition. Use LP gas resistant pipe compound to seal threaded joints.

An installer supplied, design certified gas pressure regulator must be installed to bring the gas supply pressure down to 14” w.c.

WARNING: Never connect an unregulated gas line to the heater.

IMPORTANT: Check gas line pressure before connect- ing heater to gas line. Gas line pressure must not be higher than 14” w.c. If gas line pressure is higher, heater gas pressure regulator damage could occur.

NOTE: The gas line connection can be made with 3/8” black or steel pipe. Internally tinned copper tubing may be used in certain areas. Check your local codes. Use pipe of large enough diameter to allow proper gas volume to heater. If pipe is too small, undue pressure loss will occur.

CAUTION: Use pipe joint sealant that is resistant to liquefied petroleum gases.

Install sediment trap in supply line as shown in Figure 6. Locate sediment trap where it is within reach for cleaning. Locate sediment trap where trapped matter is not likely to freeze. A sediment trap prevents moisture and contaminants from going into the heater controls. If the sediment trap is not installed or is installed wrong, the heater may not operate properly.

Test for gas leaks with a mild soap and water solution. Apply water/soap solution with brush only - do not over apply. NEVER test with an open flame.