ELECTRIC STATIONARY KETTLES
MINIMUM CLEARANCE
REQUIREMENTS AND RECOMMENDED
FLOOR DRAIN LOCATIONS
No side and back clearance required, except for operation and service requirements.
INSTALLATION PROCEDURE
Level the kettle by making necessary adjustments using the flanged feet.
1.Place a spirit level on the rim of the kettle with the cover open. Adjust the feet to level the kettle
2.Mark anchoring hole locations through the flanged feet.
3.With hole location marked, drill holes to accommodate 5/16" studs.
4.Reposition the kettle.
5.Bolt the kettle down and apply an NSF approved silicone sealant around the bolt heads and flange making contact with floor surface. Wipe off excess sealant immediately.
Fig 3. Floor Drain Location
— 6 —