SECTION 3

INSTALLATION AND INITIAL TURN-ON

Carefully measure VDC at the PV disconnect switch. The value should be the same as at the PV array string disconnect device. It should also be positive.

Close the PV disconnect switch (if present).

Carefully measure VDC across TBDC+ and TBDC- (PV +/-) terminal block. The value should be the same as at the PV array string disconnect device. It should also be positive.

Open the PV disconnect switch. The matrix capacitor bank voltage should slowly degrade to near zero over a 5-minute period.

Open all PV string disconnect switches.

System Verification

Ensure the on/off switch is disabled.

Upon applying 208 VAC power to the PV-30208, observe the LCD display on the upper enclosure. The LCD should display ‘init-FCU Version’, followed by the model number and software revision before briefly going blank. The LCD may be difficult to see depending on external light conditions. After approximately 15 seconds the panel should finish initialization. Upon completion, line 1 (system status) of the LCD should read ‘Shutdown’.

Remedy any faults reported. If the fault indicator does not change, the fault condition is still present (see Section 5). Cycling the on/off switch will reset the PV-30208 and attempt to clear any system faults. Once all faults are cleared, line 1 of the LCD will read ‘Shutdown’ indicating the PV-30208 is idle.

Close all PV array string disconnect switches (if present).

Close the main PV disconnect switch (if present).

Turn the on/off switch to the on position.

If the PV voltage is above the PV Start Voltage setpoint, and the PV Start Time is exceeded, the PV- 30208 should transition to “Power Tracking” (see Section 4, Operation).

Depending upon solar conditions, the PV-30208 may not operate at full power. If the PV array is not experiencing full sun, the PV maximum power tracker will regulate the PV voltage to maintain maximum PV power output. (See section 4 for further description of the peak power tracker).

The PV-30208 is now fully operational.

Fine Tuning

All PV-30208 operating parameters have been set at the factory, based upon prior experience with various PV arrays. Contact your Xantrex Technology distributor for further information.

It is recommended that the PV-30208 be watched during Wake-Up and Sleep Test. If the PV-30208 cycles between operating and sleeping at either of these times, the operating setpoints may not be set properly. (Refer to Section 4 for a detailed description of PV-30208 operating states). The PV- 30208 should not cycle if the setpoints are set properly.

NOTE

Some field adjustable parameters are password protected and may only be changed by trained service technicians. In particular are parameters relating to utility protection setpoints. These have been set in the factory to the limits mandated by UL1741. Any changes to these setpoints should be agreed upon by the local utility and the equipment owner.

DOCUMENT: 151315PV-30208 Photovoltaic Inverter3-8

Operation and Maintenance Manual

Copyright 2003, Xantrex Technology Inc.

Page 15
Image 15
Xantrex Technology PV-30208 important safety instructions System Verification, Fine Tuning