System Fault
System Sleep Test
System Stop
System Shutdown
EXAMPLE OF NORMAL SYSTEM OPERATION
Upon initial application of AC voltage, the LCD located on upper enclosure will display ‘Shutdown’ for approximately 15 seconds. Once the system has finished initializing, the PV-30208 will remain in standby until adequate PV voltage is available. 5 minutes after the PV start voltage has been reached, the PV-30208 will synchronize to the utility grid and begin peak power tracking the PV array. The time delay protects the inverter from excessive on/off cycling.
The PV-30208 will continue to process power until the AC output power approaches the operating losses of the inverter for a period of 5 minutes. The time delay protects the inverter from excessive on/ off cycling.