Xantrex Technology GT Series manual Interconnection Standards Compliance, Intended Use

Page 12

Safety

De-Energize/Isolation Procedure

The following procedure should be followed to de-energize the Inverter for maintenance.

WARNING

The terminals of the DC input may be energized if the PV arrays are energized. In addition, allow five minutes for all capacitors within the main Enclosure to discharge after disconnecting the Inverter from AC and DC sources.

To isolate the Inverter:

1.Turn the main ON/OFF switch (S3) to the OFF position.

2.Open the utility connection circuit breaker.

3.Open the AC Disconnect.

4.Open the DC Disconnect Switch.

5.Install lockout devices on the utility connection circuit breaker, AC and DC disconnect switch.

Interconnection Standards Compliance

The Ethernet Communications Kit complies with IEEE C37.90.1 requirements.

The Inverter complies with FCC Part 15 Class A requirements.

The Inverter is designed to meet NEC Article 690 and UL1741-2005 Static Inverters And Charge Controllers For Use In Photovoltaic Power Systems, which includes testing for IEEE 1547.1-2005, IEEE 929-2000 and IEEE 519-2000.

Intended Use

The Ethernet Communications Kit may only be used in GT Series Three Phase Grid Tie Inverters. It is not suitable for any other application areas.

x

153553

This guide for use by qualified personnel only

Image 12
Contents GT Series Three Phase Ethernet Communications Kit Page GT Series Three Phase Ethernet Communications Kit Date and Revision About This Guide PurposeScope Audience OrganizationConventions Used Related InformationImportant Safety Instructions Save These Instructions do not DiscardRisks General Safety Precautions Personal SafetySafety Equipment Qualified PersonnelOperational Safety Procedures Lockout and TagPV Terminals TB3, TB4, and TB5 PV GND De-Energize/Isolation Procedure Interconnection Standards ComplianceIntended Use Contents Xii Installation and Configuration Interface RequirementsInstallation De-Energize/Isolation Procedure ShutdownEquipment Required Installing the Ethernet Communications Kit Panel with Four M6 NutsEthernet Kit Cable Connections Configuring Energize Procedure StartupLAN Interface Set-up Configuring the LAN Interface Ethernet Communications Kit Configuration DiagramWarranty and Return Information WarrantyWarranty and Return DisclaimerReturn Material Authorization Policy Return ProcedureExclusions Out of Warranty Service Page Xantrex Technology Inc