Appendix E Troubleshooting Hardware Components

Power Supply Conditions

Se n d d o c u m e n t a t i o n c o m m e n t s t o n ex u s 5 k d o c s @ c i s c o . c o m .

Installation Best Practices

When installing the switch, follow these best practices:

Plan your site configuration and prepare the site before installing the chassis.

Verify that you have the appropriate power supplies for your chassis configuration.

Install the chassis following the rack and airflow guidelines presented in this guide.

Verify that the chassis is adequately grounded.

Initialization Best Practices

When the initial system boot is complete, verify the following:

Power supplies are supplying power to the system.

Fan modules are operating normally.

The system software boots successfully.

Switch Operation Best Practices

To ensure proper operation of your switch, take the following actions:

Make a copy of the running configuration to CompactFlash for a safe backup.

Always enter the copy running-configstartup-configCLI command after you modify the running configuration and ensure that the system is operating properly.

Never use the init system CLI command unless you understand that you will lose the running and startup configuration as well as the files stored on bootflash:.

Keep backup copies of the running kickstart and the system images on CompactFlash.

Power Supply Conditions

The two LEDs on each power supply indicate the power status for each power supply. To determine the current status for a power supply unit, note which LED is on, blinking, or off and refer to Table E-1.

 

 

 

 

Table E-1

Power Supply Conditions

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Power Supply Condition

Power LED Status

Fail LED Status

 

 

 

 

 

 

 

 

 

 

 

 

No power to all power supplies.

Off

Off

 

 

 

 

 

 

 

 

 

 

 

 

Power supply failure, including overvoltage, overcurrent,

Off

On

 

 

 

 

overtemperature, and fan failure.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Power supply warning events where the power supply

Off

Blinking

 

 

 

 

continues to operate. These events include high

 

 

 

 

 

 

 

 

temperature, high power, and slow fan.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

AC present, 3.3 voltage standby (VSB) on, and the power

Blinking

Off

 

 

 

 

supply unit is off.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Power supply on and OK.

On

Off

 

 

 

 

 

 

 

 

 

 

 

 

Cisco Nexus 6000 Series Hardware Installation Guide

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

E-2

 

 

 

 

 

OL-15902-02

 

 

 

 

 

 

 

 

Image 66
Contents Cisco Nexus 6000 Series Hardware Installation Guide Americas HeadquartersPage Organization PrefaceAudience Chapter and Title DescriptionConventions Bewaar Deze InstructiesWarnung Wichtige Sicherheitshinweise Avvertenza Importanti Istruzioni Sulla SicurezzaAviso Instruções Importantes DE Segurança Spara Dessa Anvisningar GEM Disse Anvisninger Viii Preface Obtaining Documentation and Submitting a Service Request Related DocumentationCisco Nexus 6004 Switch FeaturesOverview Front View of the Cisco Nexus 6004 switch ChassisRear View of the Cisco Nexus 6004 Switch Expansion ModulesPorts Cisco Nexus 6004 Expansion ModulePower Supply Part Number Power SupplyFan Module Airflow Transceivers Cisco SFP DescriptionOverview Cisco Nexus 6004 Switch Installing the Cisco Nexus 6000 Series Switches Chassis Weight Preparing for InstallationInstallation Options with Racks and Cabinets Installation GuidelinesPage Unpacking and Inspecting the Switch Required EquipmentInstalling the Switch Installing a Cisco Nexus 6004 switchQuantity Part Description Cisco Nexus 6000 Series Hardware Installation Guide Grounding the Switch Proper Grounding Practices Environment Severity Level Grounding RecommendationsPreventing Electrostatic Discharge Damage OL-15902-01 Establishing the System Ground Required Tools and EquipmentGrounding the Cisco Nexus 6000 Series Chassis Starting the Switch Statement Cisco Nexus 6000 Series Hardware Installation Guide Connecting the Switch Connecting to the Console Port Preparing for Network ConnectionsInstalling and Replacing Transceivers Connecting to the Ethernet Connector PortConnecting to an Ethernet Port Installing a TransceiverReplacing a Transceiver Installing Cables into Transceivers Installing a Cable into an TransceiverReplacing a Cable for a Transceiver Connecting the Switch Connecting to an Ethernet Port Replacing Components Replacing Expansion ModulesReplacing LEMs Removing a LEMReplacing Modules Installing a LEMInstalling a Module Removing a ModuleReplacing or Installing Power Supplies Removing a Power SupplyInstalling a Power Supply Wiring a DC Power Connector Wiring the DC Power Connector Installing a Fan Module Replacing a Fan ModuleRemoving a Fan Module Removing the Cisco Nexus 6000 Platform Chassis Cabinet and Rack Installation Cabinet and Rack RequirementsGeneral Requirements for Cabinets and Racks Cable Management Guidelines Requirements Specific to Perforated CabinetsEnvironmental Specifications Technical SpecificationsSwitch Specifications Description SpecificationSpecifications for the Cisco Nexus 6004 Power Supply Expansion Module SpecificationsPower Specifications Property Cisco Nexus 6004SwitchAppendix B Technical Specifications Appendix B Technical Specifications Cable and Port Specifications Cable RJ-45 Connector PinoutsSignal Name P1, P1-45 Pins P2, DB-9 Pins Length Supported Power Cords and PlugsConsole Port Description Feet Meters IllustrationCAB-N5K6A-NA CAB-9K10A-AU Plug CAB-9K10A-SW CAB-C13-CBN Jumper Power Cord Figure C-14Indicator Location Function Color Status State LEDsChassis and Module LED Descriptions Conditions Indicated by the Power Supply LEDs Power Supply Condition Green AmberPort LEDs Status Description Ethernet Port LEDsEthernet and Fibre Channel LEDs Link State LED StateAppendix D LEDs Port LEDs Troubleshooting Hardware Components Switch Hardware Best PracticesOverview Switch Operation Best Practices Power Supply ConditionsInstallation Best Practices Power Supply Condition Power LED Status Fail LED StatusPage Cisco Nexus 6000 Series Hardware Installation Guide Accessory Kits Cisco Nexus 6004 Switch Accessory KitOL-15902-02-xx Site Planning and Maintenance Records Site Preparation ChecklistTask No Planning Activity Verified By Time Date Contact and Site Information Chassis and Module Information Slot Module Type Module Serial Number Supervisor
Related manuals
Manual 204 pages 40.67 Kb