Extron electronic 200, 300C, 300S, 600, 800 user manual Installing the power module CC 300, 600

Page 11

Installation, cont’d

Installing the power module (CC 300, 600, 800)

From the underside of the Cable Cubby, gently push the power module into the desired position at the desired elevation. Secure the power module into position with four Phillips head screws.

Installing the cables

Three half-moon cutouts in each set of cable pass-through (split) AAPs loosely channel three cables in the cubby. Each channel is padded with a split grommet to prevent cable wear. Each channel and each associated split grommet is a different size (figure 2-5).

 

Large

Small

Small

 

Medium

Medium

Medium

 

Small

Large

Large

Cable hole

Hole size

Grommet size

Large

0.625" (1.59 cm)

0.453" (1.15 cm)

Medium

0.562" (1.43 cm)

0.390" (0.99 cm)

Small

0.5" (1.27 cm)

0.312" (0.79 cm)

Figure 2-5 — Cable pass-through AAPs

A typical installation consists of a VGA cable, an audio cable, and a network cable. In a typical installation, the VGA cable runs in the largest channel, the network cable runs in the middle (medium) channel, and the audio cable runs in the smaller channel. In a non-standard installation, just match the diameter of the cable to the size of the channel as best you can.

Install cables in the channels as follows:

1.

Remove a segment of a set of split AAPs by unscrewing

 

the nuts on the underside of the bracket that fastens the

 

plate to the shelf (CC 200) or shelf bracket (CC300, 600, or

 

800) (figure 2-4, on page 2-7).

2.

Rest the cables in the half-moon cutouts of the split AAP

 

segment still mounted on the shelf (CC 200) or shelf

 

brackets (CC 300, 600, and 800). Place the cables so that

 

the connectors that require inside Cable Cubby access

 

protrude from the front (black side) of the split AAP

 

segment.

3.

Insert the screws of the split AAP segment that you

 

removed in step 1 through the holes in the shelf bracket.

 

Ensure that the cables are free in the channels that the two

 

split AAP segments form without being pinched where the

 

two segments meet.

4.

Secure the split AAP segment to the shelf (CC 200) or shelf

 

brackets (CC 300, 600, and 800) with the provided captive

 

washers and #4-40 nuts.

5.

Slip the appropriate size split grommet over each cable

 

with the flange of the grommet toward the connector

 

that will be accessible inside the Cable Cubby. Snap the

 

grommets into the channels.

6.

If applicable, snap the included hole plugs into unused

 

channels in place of the split grommets.

Installing the AAPs

The split AAPs can be replaced with passive Extron AAPs.

Replace a set of split AAPs as follows:

1.

Remove the set of split AAPs to be replaced by unscrewing

 

the nuts on the underside the shelf (CC 200) or shelf

 

bracket (CC 300, 600, and 800) that fasten the plates to the

 

bracket (figure 2-4, on page 2-7).

2.

Cable the rear of the AAP(s) to be installed before attaching

 

the AAPs to the enclosure.

3.

Insert the screws of the AAPs through the holes in the shelf

 

or shelf bracket. Secure the AAPs to the shelf brackets with

 

the provided captive washers and #4-40 nuts.

2-8

Cable Cubby® Products • Installation

Cable Cubby® Products • Installation

2-9

Image 11
Contents Cable Cubby Page Table of Contents Cable Cubby Products Table of Contents, cont’dIntroduction About the Cable Cubby Products IntroductionIntroduction, cont’d FeaturesTwo InstallationPreparing the Routing Template InstallationInstallation Overview Preparing the table with a router Installation, cont’d Preparing the TableAAP shelf brackets CC 300, 600 Installation, cont’dInstalling the Cables and AAPs Preparing the table with a hole saw Cable Cubby 300C onlyInstalling the AAPs Installing the power module CC 300, 600Installing the cables Mounting the Cable Cubby Installing the shelf assembly CC 300, 600Adjusting the cable position CC Cable Cubby 300C Maintenance and Modifications Removing and Replacing the Cable Cubby Maintenance and ModificationsReplacing Cables or an AAP Maintenance and Modifications, cont’dInternational Cable Cubby 600 with second power module Cable Cubby 600 with second power module Reference Information Installing the power moduleGeneral Reference InformationSpecifications Cable Cubby Packaging for Shipment, cont’dCable Cubby Part number Cable Cubby Part NumbersPackaging for Shipment, cont’d Included Parts Replacement/Modification Part NumbersRouting Template Part Numbers Top Plate DimensionsCable Cubby Cable Cubby 300C Cable Cubby Packaging for ShipmentFigure B-1 Cable Cubby return kit Packaging for ShipmentFigure B-3 Removing center foam Figure B-7 Placing the cubby in the carton Packaging for Shipment, cont’d Packaging for Shipment Extron’s Warranty Precautions