4. THEORY OF OPERATION page 30

4.2.4. Channel Card, RCS-110:

Refer to "RCS-110 Schematic Diagram" Drawing 6 and "RCS-110 Component Designator" Drawing 7 (Appendix F.).

VR1, VR2, and VR3 regulate the ±15 volt power supply voltages to ±12 volts and +5 volts for use on this card. The card is equipped with a series of test points for discriminator, pulse amplitude, and high voltage measurements. The high voltage test point is a 100 to 1 divider.

U12, U13, and the associated circuitry make up the regulated high voltage power supply. High voltage (less than 1,500Vdc) is supplied to the MHV connector on the backplane via the 44 pin edge card connector.

Pulses from the detectors are input through shielded MHV cables to the rack control module, and then into the inputs on the backplane to the channel boards. The analog signal is decoupled by C46, amplified by U8 and U7, and sent to the single channel analyzer. The second amplifier/SCA channels are not used in this application.

The SCA is made up of two voltage comparators (U6). The amplified signal must fall between the LLD and ULD levels to be digitized and sent to the counters in the computer. These voltages can be manually adjusted, or set by the computer. In either case, the actual adjustment is done on the RCS-120 card.

Any pulses having an amplitude greater than the LLD and less than the ULD pass through the comparator circuits and generate a digital pulse (U10). These pulses are sent to a differential line transmitter (U2) and on to the line receivers on the CIF-553 Computer Interface board, which plugs into the ISA bus in the computer.

Model BM-286A

Image 33
Contents Waste Monitor Model BM-286A Inspection and Installation Table of ContentsMaintenance Theory of OperationAppendix Warranty Glossary Formulas TroubleshootingConfiguration Tracking Sheet Parts Recommended Spare Parts Spare Parts Ordering InformationScope and Purpose of Manual IntroductionSpecifications Introduction Introduction Inspection Installation General Overview Operating InstructionsPOWER-UP and SELF-TESTS Level One Access Access MenuPCA-II Normal Operation Operating Instructions Programming the System Abcdefgh SET-UP MenuOperating Instructions Operating Instructions Waste Stream Parameters Operating Instructions Operating Instructions Operating Instructions This value is used only when the Alarm Type is set to DPM Utilities Menu Operating Instructions Reports Initial Installation Checklist Operating Instructions BM-286A Waste Stream SET-UP Worksheet Unit Operation Theory of Operation Theory of Operation Theory of Operation Theory of Operation Operator Maintenance Maintenance Maintenance Settings for Plastic Detectors LLDULD Weight Calibration Maintenance Diagnostic Aids Fault Isolation Computers Longs Peak Court LONGMONT, Colorado Appendix B. Glossary Appendix B. Glossary Activity from Counts Reliable Detectable Activity RDA Formula Variance System Modifications Configuration Tracking SheetLongs Peak Court LONGMONT,COLORADO Drawings