Dell 7000 Series Initiating a Warm Failover of the Manager Unit, Nonstop Forwarding Scenario

Page 25

Stacking Dell PowerConnect 7000 Series Switches

To take full advantage of nonstop forwarding, layer 2 connections to neighbors should be via port channels that span two or more stack units, and layer 3 routes should be equal-cost multi-path (ECMP) routes. ECMP provides load balancing, using multiple next hops to a single destination via

physical ports on two or more units. The hardware can quickly move traffic flows from port channel members or ECMP paths on a failed unit to a surviving unit.

Initiating a Warm Failover of the Manager Unit

The administrator can use the initiate failover command to initiate a "warm" restart. This command reloads the management unit, triggering the standby unit to take over. As the standby management unit takes over, the system continues to forward end-user traffic. The end-user data streams switched over the failing switch may lose a few packets during the failure, but they do not lose their IP sessions, such as VoIP calls.

If no standby unit is available when the initiate failover command is issued, the command fails with an error message stating that no standby unit exists. If the standby unit is not ready for a warm restart, the command fails with a similar error message.Administrators should be aware that use of the movemanagement command is not recommended in operational networks as network traffic interferes with stack convergence. The movemanagement command performs a full synchronization and then triggers a cold restart, even if the target unit is the backup unit, and is therefore less preferred than

the initiate failover command.

Nonstop Forwarding Scenario

Figure# 6 depicts the following network setup:

Host 1 is a video stream server. Hosts 2 and 3 are video stream receivers.

The stack has OSPF and PIM-SM adjacencies with Router 1 over a LAG with member ports in unit 1 and unit 2.

Spanning tree runs on the links in the L2 network connecting the stack, Switch 1, and Switch 2.

The stack runs IGMP on the links toward Host 2 and Host 3.

VLAN 20 is a routing VLAN with IP address 192.168.20.2 on the stack.

The network is configured to select Switch 2 as the root bridge. The stack selects its direct link to Switch 2 as its root port. The stack puts its link to Switch 1 in the Discarding state.

Router 1 is a Cisco router that serves as a static rendezvous point (RP) in the PIM-SM network.

The CLI for configuring this scenario follows the illustration, along with a description of how the stack responds during a failover with NSF enabled and disabled.

Page 23

Image 25
Contents Dell Technical White Paper Stacking Dell PowerConnect Series SwitchesStacking Dell PowerConnect 7000 Series Switches Contents Applicability IntroductionStacking and Management Stacking and Redundancy Stacking and PerformanceDual Stacking Modules Configured in a Ring Power-Up Sequencing Considerations Mixing M6348 and PC7000 Series Switches in a StackConsole#boot auto-copy-sw allow-downgrade Initial Installation and Power-up of a Stack Selecting the Standby Unit Selecting the Master UnitUpdating the Firmware on a Stack Automatic UpdateManual Update FTP Creating a Separate Vlan for File DownloadsFrom the Switching Vlan Vlan Membership page, click Add Navigate to the Routing IP IP Interface Configuration Page Stacking Dell PowerConnect 7000 Series Switches Click Apply Adding a Stack Member with Minimal Interruption Removing a Stack Member with Minimal Interruption Master Failover Merging Two Operational StacksEffect of Master Failover on PoE Devices Failover Scenarios Stack Member FailoverScenario Stack Split Stack Split with Manager Failure Nonstop Forwarding Nonstop Forwarding Scenario Initiating a Warm Failover of the Manager UnitNonstop Forwarding Example Router NSF Scenario Configuration via CLIStack Switch Switch NSF Example Parameter Timing NSF Re-convergence TimingSmall Configuration Stacking CLI CommandsSummary Stacking Web Interface