The recommended procedure for merging two operational stacks is as follows:

Caution! This procedure is disruptive and requires a network outage.

1.Always power off all units in one stack before connecting to another stack.

2.Add the units as a group by unplugging one stacking cable in the operational stack and physically connecting all unpowered units.

3.Completely cable the stacking connections, making sure the redundant link is also in place.

Two operational stacks can also be merged by reconnecting stack cables without powering down units in either stack. Connecting a powered-up standalone unit to an existing stack leads to same behavior as when merging two operational stacks. In such cases, manager election is performed and the manager unit with the higher MAC address is chosen as manager. The stack that no longer has a stack manager resets itself and all of its member units. After the reset, all the stack members in the reset stack join the stack that has the manager to form a single stack. The stack that has the manager remains functional through the merge process.

Synchronizing the Running Configuration between the Master and Standby Units

The master unit copies its running configuration to the standby unit whenever the configuration changes (subject to some minimal time delays introduced in the copy mechanism to increase the efficiency of the transfer process). This enables the standby unit to take over the stack operation with minimal interruption if the master unit becomes unavailable.

The running-config synchronization also occurs:

When the administrator saves the running configuration to the startup configuration on the master unit.

When the standby unit changes.

Master Failover

If the current master unit fails, the standby unit becomes the master unit. If no switch is preconfigured as the standby unit, the firmware automatically selects a standby unit from the existing stack units.

When the failed master resumes normal operation, it joins the stack as a member (not a master) if the new master unit has already been elected.

The stack supports nonstop forwarding and graceful restart during a master failover. See “Nonstop Forwarding” on page 22.

Effect of Master Failover on PoE Devices

Stack members that provide power-over-Ethernet (PoE) to connected devices continue to provide power in the event of a master failover. The PoE application uses a separate controller on each unit, and these controllers are not initialized upon a warm restart.

Page 18

Image 20
Contents Stacking Dell PowerConnect Series Switches Dell Technical White PaperStacking Dell PowerConnect 7000 Series Switches Contents Stacking and Management IntroductionApplicability Stacking and Performance Stacking and RedundancyDual Stacking Modules Configured in a Ring Mixing M6348 and PC7000 Series Switches in a Stack Power-Up Sequencing ConsiderationsConsole#boot auto-copy-sw allow-downgrade Initial Installation and Power-up of a Stack Selecting the Master Unit Selecting the Standby UnitAutomatic Update Updating the Firmware on a StackManual Update Creating a Separate Vlan for File Downloads FTPFrom the Switching Vlan Vlan Membership page, click Add Navigate to the Routing IP IP Interface Configuration Page Stacking Dell PowerConnect 7000 Series Switches Click Apply Adding a Stack Member with Minimal Interruption Removing a Stack Member with Minimal Interruption Effect of Master Failover on PoE Devices Merging Two Operational StacksMaster Failover Scenario Stack Member FailoverFailover Scenarios Stack Split Stack Split with Manager Failure Nonstop Forwarding Initiating a Warm Failover of the Manager Unit Nonstop Forwarding ScenarioNonstop Forwarding Example NSF Scenario Configuration via CLI RouterStack Switch Switch NSF Example NSF Re-convergence Timing Parameter TimingStacking CLI Commands Small ConfigurationStacking Web Interface Summary