8e6 Technologies MSA-004-005 quick start Optional Install the Traditional UP Racks

Page 13

Optional: Install the Traditional UP Racks

After you have installed the inner rails on the chassis, you are ready to install the outer rails of rail assemblies to the rack.

NOTE: The rails are designed to fit in the racks with the depth of 28” to 33”.

Determine the placement of each component in the rack before you install the rails.

Install the heaviest server components on the bottom of the rack first, and then work up.

1.In the package, locate a pair of front (short) and rear (long) brackets. Please note that the brackets are marked with Up/Front Arrows (front) and Up/Rear arrows (rear).

2.Secure the front (short) bracket (marked with the Up/Front arrows) to the outer rail with two Type G screws. (See the previous page for a description of the Type G screw.)

3.Attach the rear (long) bracket to the other end of the outer rail and secure the rear (long) bracket to the outer rail with a Type G screw as shown below.

4.Measure the depth of your rack and adjust the length of the rails accordingly.

5.Repeat the same steps to install the other outer rail on the chassis.

6.Secure both outer rail assemblies to the rack with Type H screws and Type I wash- ers. (See the previous page for descriptions of Type H and Type I hardware compo- nents.)

8e6 ProxyBlocker Quick Start Guide



Image 13
Contents Guide 8e6 ProxyBlocker Quick Start Guide Contents 8e 6 Proxy Blocker Quick Start Guide 8e6 ProxyBlocker Introduction Conventions Used in this Document About this Document8e6 Corporate Headquarters USA Procedures8e6 Taiwan Unpack the Unit from the Carton Select a Site for the Server Rack Mount the Server Rack Setup PrecautionsRack Mount Instructions Optional Install the Chassis Rails8e6 ProxyBlocker Quick Start Guide Optional Install the Traditional UP Racks 8e6 ProxyBlocker Quick Start Guide Optional Install the Open Racks 8e6 ProxyBlocker Quick Start Guide 8e6 ProxyBlocker Quick Start Guide Install the Chassis into the Rack Power Supply Precautions Check the Power SupplyServer Operation and Maintenance Precautions General Safety InformationElectrical Safety Precautions AC Power Cord and Cable PrecautionsMotherboard Battery Precautions Wizard Setup Requirements Setup ProceduresAdministrator Console Setup Requirements Monitor and Keyboard Setup Wizard Setup ProceduresSerial Console Setup Link the Workstation to the ProxyBlockerHyperTerminal Setup Procedures 8e6 ProxyBlocker Quick Start Guide 8e6 ProxyBlocker Quick Start Guide System Configuration Screen Login screenSystem Configuration Administration menu Log Off, Disconnect the Peripherals System Status ScreenPreliminary Setup Console Setup ProceduresWorkstation Configurations Boot Up Process Access the ProxyBlocker Administrator Console Network SetupLog in to ProxyBlocker Administrator Console Network Network Operation Mode Network LAN Settings Network NTP Servers Network Regional Setting Physically Connect the ProxyBlocker to the Network Test the ProxyBlocker Console Connection Test Filtering Set Library UpdatesActivate and Register the ProxyBlocker Perform a Complete Library Update Monitor the Library Update Process Conclusion LED Indicator Color Condition Description LED Indicator Key Button KeyMSA Units Declaration of the Manufacturer or Importer Safety ComplianceElectromagnetic Compatibility EMC Electromagnetic Compatibility Class a NoticeEC Declaration of Conformity Index Wizard setup 19 8e6 ProxyBlocker Quick Start Guide