Nortel Networks 8010co Power terminal block, Configuring standalone BIPs to report alarm status

Page 27

Chapter 1 Overview 27

This type of configuration allows you to independently monitor and control the external audible and visual alarm status indications of the BIP at the central office.

Figure 8 Configuring standalone BIPs to report alarm status

1

J1

J2

J3

J4

J5

3 2 1 3 2 1

 

3 2 1 3 2 1 A1 A2 B1 B2

PS (+)

PS (+)

A/B Input Feed

PS (-)

PS (-)

– 48 VDC

Lower Shelf

Upper Shelf

Returns

Lower Shelf

Upper Shelf

A/B Input Feeds

To central office

 

 

 

 

 

 

 

 

 

BIP 1

3 2 1 3 2 1

 

3 2 1 3 2 1 A1 A2 B1 B2

PS (+)

PS (+)

A/B Input Feed

PS (-)

PS (-)

– 48 VDC

Lower Shelf

Upper Shelf

Returns

Lower Shelf

Upper Shelf

A/B Input Feeds

To central office

BIP 2

3 2 1 3 2 1

 

3 2 1 3 2 1 A1 A2 B1 B2

PS (+)

PS (+)

A/B Input Feed

PS (-)

PS (-)

– 48 VDC

Lower Shelf

Upper Shelf

Returns

Lower Shelf

Upper Shelf

A/B Input Feeds

To central office

BIP 3

1 = J5 (standalone office alarm connector)

10419EA

Power terminal block

The power terminal block is located on the back panel of the BIP. As shown in Figure 9 on page 28, the power terminal block provides 21 connection blocks for DC input and output feeds.

Installing the Breaker Interface Panel for the Ethernet Routing Switch 8010co Chassis

Image 27
Contents Part No -G Rev May Great America Parkway Santa Clara, CA International regulatory statements of conformity Copyright 2006 Nortel Networks. All Rights ReservedTrademarks Statement of conditionsVcci statement Japan/Nippon only CE marking statement Europe onlyEN 60 950 statement Nortel Inc. software license agreementGeneral Rev Contents Rev ContentsIndex Contents Rev Figures Rack grounding strip example Tables Tables Rev Before you begin PrefacePreface How to get HelpText conventions Getting Help from the Nortel Web siteGetting Help through a Nortel distributor or reseller Getting Help over the phone from a Nortel Solutions CenterPreface Rev Physical description Chapter OverviewFront panel Shelf circuit breakers upper and lower shelvesOverview Shelf circuit breakers Alarm module display LEDs Alarm module display panelMajor Shelf alarm connectors upper and lower shelves Back panelFront panel locking screws Shelf alarm connections upper and lower shelves Configuring multiple BIPs to aggregate office alarms Central office alarmsConfiguring standalone BIPs to report alarm status Power terminal block1 3 2 1 3 2 1 a 1 a 2 B 1 B Power and grounding example Opening the front panel Accessing the alarm moduleAccessing the alarm module 8010co chassis configuration with BIP option Configuration examplePreparing to install the breaker interface panel Chapter InstallationShipment contents DC input electrical requirements DC power requirementsAdditional equipment Mounting hardwareInstalling the hardware Installing the breaker interface panelRemoving the plastic back cover from the BIP Connecting cables to the chassis power supplies Removing the 8010co chassis bottom 312096-A bezel Location of power supplies Loosening the power supply retaining screws +DC -DC Power supply cables Attaching the positive lead +DC -DC Replacing the power supply Labeling cables for the BIP Routing power supply cables to the BIPRack grounding strip example Connecting the ground cables to the rack grounding stripAttaching power supply cable leads to the BIP Connecting the power supply cables to the BIPLocate the BIP ground cable see on Attaching the BIP ground cable Connecting DC input power feeds to the BIP Single chassis and dual chassis input options B feed exampleLocating the a and B -48 VDC input feeds Connecting the a and B -48 VDC input feeds to the BIP 1 Connecting the a and B -48 VDC input feeds to the BIP 2 Connecting the A/B input feed returns 1 Go to the next section, Replacing covers on Replacing the plastic back cover on the BIP Replacing coversGo to the next section, Installing shelf alarm cables on Installing shelf alarm cables Installing shelf alarm cablesVerifying the installation Verifying the LEDs Initial power-upPowering off the system Installation Installation Rev Chapter Problem solving Interpreting the LEDs Problem solvingOr a problem in circuits that are not essential to Diagnosing and correcting the problem Corrective actions Corrective actionsProblem solving Corrective actions Environmental Appendix a Technical specificationsElectrical Physical dimensionsSafety agency certification Appendix a Technical specificationsAppendix B BIP external cable pin assignments Shelf alarm connectors J1 and J2Appendix B BIP external cable pin assignments J1 and J2 shelf alarm connector pin assignmentsJ3 and J4 high-density 26-pin D-sub connector Office alarm connectors J3 and J4J3 and J4 office alarm connector pin assignments J5 high-density 26-pin D-sub connector Standalone office alarm connector J5J5 standalone office alarm connector pin assignments Numbers IndexIndex