33
Chapter 2
Installation
This chapter describes how to install the breaker interface panel and covers the following topics:
•“Preparing to install the breaker interface panel” next
•“Installing the breaker interface panel” on page 36
•“Verifying the installation” on page 62
Preparing to install the breaker interface panel
Before begin the installation, verify that:
•Your shipment is complete and undamaged.
•You have the cables, tools, and other equipment that you need.
•Your installation site meets the physical, electrical, and environmental requirements (see Appendix A, “Technical specifications,” on page 73).
The sections that follow help you prepare for installation.
Note: For a list of requirements that must be met for the 8010co chassis, see the appropriate product chassis installation manual.
Installing the Breaker Interface Panel for the Ethernet Routing Switch 8010co Chassis