American Power Conversion PD60L6FK1, PD60G6FK1 Top-level status screens, Top-level menu screen

Page 22

PDU Display Interface

Top-level status screens

After system start-up, the display interface displays a brief start-up screen and then scrolls automatically and continuously through four screens of basic status information. Press the Up and Down arrow keys to interrupt the automatic scrolling if you wish to view a specific status screen.

 

 

 

Volts In

Volts Out

L1-2: 000

L1: 000

L2-3: 000

L2: 000

L3-1: 000

L3: 000

 

 

 

 

Total Output Loading

kW:

000

PF: 000

kVA:

000

%LD: 000

Freq:

00.0

 

 

 

 

Load Current

L1: 000 Neut:000

L2: 000

L3: 000

No Active Alarms

System Date/Time:

Jun-24 2003 07:58

Top-level menu screen

On any top-level status screen, press the ENTER key to open the top-level menu screen.

 

 

 

 

 

 

Load-Meter

Alarms

 

 

Volt-Meter

Panel

 

 

Contacts

Config

 

 

Breakers

Help

 

 

 

 

If the display interface is inactive for the time specified as the Time-outsetting, the interface reverts to the initial basic monitoring screens.

Note

For descriptions of the top-level menu choices, see the individual sections starting on page 16.

Navigating through screens

To open any screen, press the Up and Down arrow keys until the selector arrow ( rests next to your desired selection. Press the ENTER key to view the selected screen.

 

 

 

 

 

 

Load-Meter

Alarms

 

 

Volt-Meter

Panel

 

 

Contacts

Config

 

 

Breakers

Help

 

 

 

 

Contacts In: 02of04

Name: User Switch #2

Normal:Open

Status: Open

When configuring settings, press the Up and Down arrow keys until the selector arrow ( rests next to the setting you want to change, and press the ENTER key. If the setting is a list of choices, an input arrow ( will appear next to the setting. Press the Up and Down arrow keys until your desired change is listed. Press the ENTER key to select the setting.

Contacts In: 02of04

Name: User Switch #2

Normal:Open

Status: Open

14

60 kW InfraStruXure PDU — Operation and Configuration

Image 22
Contents 60kW InfraStruXure PDU Page Audience How to find updates to this manualAbout This Manual Companion manualsPage Contents Operation Specifications Product Information Cross-reference symbols used in this manual SafetySafety symbols used in this manual OverviewReceiving/moving Installation/MaintenanceInput Voltage Circuit Breaker Sizing Total power off procedure Emergency Power Off EPOEMI InfraStruXure PDU OverviewFront view Front view interior Rear view of PDU with transformer interior PDURear view of PDU without transformer interior PDU monitoring unit User connection plate Multi-Branch Cordset Adapters SKU #Compatible APC 208V PDUs PDU Display Interface       Top-level menu screen Top-level status screensNavigating through screens Password-protected screens Power Factor Load-Meter ScreenVolt-Meter Screen Input Contacts Contacts ScreenOverview Open or ClosedAlarm Relay Map Relay output. For example, AlarmHow to connect contacts to the PDU monitoring unit Breakers Screen Main InputEntire Log Alarms ScreenNew Logged Items Clear LogLoading Limits Global AlarmConfig Voltage LimitsPDU Alarms Alarm Condition ExplanationBranch Ckt Loading Panel ScreenBranch Ckt Limits Circuit breakers occupying positions 08, 10, and 12 on Panel ConfigurationTop right distribution panel Global Panel Config System/Network Config ScreenSystem Password Date/TimeOutput Config Electrical ConfigInput Config Manufacturer DataFactory Defaults Firmware UpdatesHow to Apply Power to the System OperationFor PDUs with and without a transformer How to Ensure Total Power Off For PDU with transformer Open turnPage InfraStruXure Manager Communication ConfigurationInfraStruXure PDU Management Options Network management interfacesConfiguring the InfraStruXure Manager Connect the InfraStruXure PDU to the InfraStruXure ManagerConfiguration Overview Configuring the Network Management InterfaceConnect the InfraStruXure PDU to your network TCP/IP configuration methods Device IP Configuration WizardBootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where Use apc for the User Name and Password Local access to the control consoleRemote access to the control console Control console Use apc for both User Name and PasswordChoose Network from the Control Console menu Quick-Start manual for access information Web interfaceSnmp FTP and SCP KW InfraStruXure PDU-Operation and Configuration Important Safety Instructions Customizing and Updating the PDUPDU Orderable Part List Power CablesCircuit Breakers Customizing and Updating the PDU Add a power cable to the PDU How to Add Circuit Breakers and Power CablesAdd a circuit breaker on the PDU Customizing and Updating the PDU ATS 0 ATS 1 ATS Atsen How to connect contacts to the PDU monitoring unit How to Test the EPO Switch To test your EPO wiring and switchesSafety warnings Customizing and Updating the PDU Upgrading the PDU monitor processor How to Download Firmware UpgradesFrom a local computer Xmodem Specifications 60kW InfraStruXure PDUCompliance InfraStruXure Standard Warranty Product InformationProduct Information APC Three-Phase Systems Life-Support PolicyHow to Obtain Service How to contact APCGeneral changes Appendix Changes in This ManualChanges by page number Page Index 60kW InfraStruXure PDU-Operation and Configuration Page Page Page APC Worldwide Customer Support