How to Ensure Total Power Off

1. Open (turn OFF) the main circuit breaker on the power source feeding the PDU.

2. Open (turn OFF) the Main Input on the InfraStruXure PDU.

3.For PDU with transformer: Open (turn

OFF) the Main Output circuit breakers on the front of the InfraStruXure PDU.

60 kW InfraStruXure PDU—Operation and Configuration

33

Image 41
Contents 60kW InfraStruXure PDU Page About This Manual How to find updates to this manualAudience Companion manualsPage Contents Operation Specifications Product Information Safety symbols used in this manual SafetyCross-reference symbols used in this manual OverviewInput Voltage Circuit Breaker Sizing Installation/MaintenanceReceiving/moving Emergency Power Off EPO Total power off procedureEMI Front view OverviewInfraStruXure PDU Front view interior PDU Rear view of PDU with transformer interiorRear view of PDU without transformer interior PDU monitoring unit User connection plate SKU # Multi-Branch Cordset AdaptersCompatible APC 208V PDUs        PDU Display InterfaceNavigating through screens Top-level status screensTop-level menu screen Password-protected screens Load-Meter Screen Power FactorVolt-Meter Screen Overview Contacts ScreenInput Contacts Open or ClosedRelay output. For example, Alarm Alarm Relay MapHow to connect contacts to the PDU monitoring unit Main Input Breakers ScreenNew Logged Items Alarms ScreenEntire Log Clear LogConfig Global AlarmLoading Limits Voltage LimitsAlarm Condition Explanation PDU AlarmsBranch Ckt Limits Panel ScreenBranch Ckt Loading Top right distribution panel Panel ConfigurationCircuit breakers occupying positions 08, 10, and 12 on Global Panel Config System Password Config ScreenSystem/Network Date/TimeInput Config Electrical ConfigOutput Config Manufacturer DataFirmware Updates Factory DefaultsOperation How to Apply Power to the SystemFor PDUs with and without a transformer For PDU with transformer Open turn How to Ensure Total Power OffPage InfraStruXure PDU Management Options Communication ConfigurationInfraStruXure Manager Network management interfacesConnect the InfraStruXure PDU to the InfraStruXure Manager Configuring the InfraStruXure ManagerConnect the InfraStruXure PDU to your network Configuring the Network Management InterfaceConfiguration Overview Device IP Configuration Wizard TCP/IP configuration methodsBootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where Remote access to the control console Local access to the control consoleUse apc for the User Name and Password Choose Network from the Control Console menu Use apc for both User Name and PasswordControl console Web interface Quick-Start manual for access informationSnmp FTP and SCP KW InfraStruXure PDU-Operation and Configuration Customizing and Updating the PDU Important Safety InstructionsCircuit Breakers Power CablesPDU Orderable Part List Customizing and Updating the PDU Add a circuit breaker on the PDU How to Add Circuit Breakers and Power CablesAdd a power cable to the PDU Customizing and Updating the PDU ATS 0 ATS 1 ATS Atsen How to connect contacts to the PDU monitoring unit To test your EPO wiring and switches How to Test the EPO SwitchSafety warnings Customizing and Updating the PDU From a local computer How to Download Firmware UpgradesUpgrading the PDU monitor processor Xmodem 60kW InfraStruXure PDU SpecificationsCompliance Product Information InfraStruXure Standard WarrantyProduct Information Life-Support Policy APC Three-Phase SystemsHow to contact APC How to Obtain ServiceChanges by page number Appendix Changes in This ManualGeneral changes Page Index 60kW InfraStruXure PDU-Operation and Configuration Page Page Page APC Worldwide Customer Support