Operation

How to Apply Power to the System

1. Close (turn ON) the main circuit breaker of the power source supplying power to the PDU.

2. Close (turn ON) the Main Input on the InfraStruXure PDU.

3. Power the PDU distribution circuit breakers:

a. For PDU with transformer: Close (turn ON) the Main Output circuit breaker on the PDU.

After the Main Output circuit breaker has been closed (turned ON), both PDU distribution panels will be energized.

Note

60 kW InfraStruXure PDU—Operation and Configuration

31

Image 39
Contents 60kW InfraStruXure PDU Page Companion manuals How to find updates to this manualAbout This Manual AudiencePage Contents Operation Specifications Product Information Overview SafetySafety symbols used in this manual Cross-reference symbols used in this manualInstallation/Maintenance Receiving/movingInput Voltage Circuit Breaker Sizing Emergency Power Off EPO Total power off procedureEMI Overview InfraStruXure PDUFront view Front view interior PDU Rear view of PDU with transformer interiorRear view of PDU without transformer interior PDU monitoring unit User connection plate SKU # Multi-Branch Cordset AdaptersCompatible APC 208V PDUs        PDU Display InterfaceTop-level status screens Top-level menu screenNavigating through screens Password-protected screens Load-Meter Screen Power FactorVolt-Meter Screen Open or Closed Contacts ScreenOverview Input ContactsRelay output. For example, Alarm Alarm Relay MapHow to connect contacts to the PDU monitoring unit Main Input Breakers ScreenClear Log Alarms ScreenNew Logged Items Entire LogVoltage Limits Global AlarmConfig Loading LimitsAlarm Condition Explanation PDU AlarmsPanel Screen Branch Ckt LoadingBranch Ckt Limits Panel Configuration Circuit breakers occupying positions 08, 10, and 12 onTop right distribution panel Global Panel Config Date/Time Config Screen System Password System/NetworkManufacturer Data Electrical ConfigInput Config Output ConfigFirmware Updates Factory DefaultsOperation How to Apply Power to the SystemFor PDUs with and without a transformer For PDU with transformer Open turn How to Ensure Total Power OffPage Network management interfaces Communication ConfigurationInfraStruXure PDU Management Options InfraStruXure ManagerConnect the InfraStruXure PDU to the InfraStruXure Manager Configuring the InfraStruXure ManagerConfiguring the Network Management Interface Configuration OverviewConnect the InfraStruXure PDU to your network Device IP Configuration Wizard TCP/IP configuration methodsBootp & Dhcp configuration Option 43 = 01 04 31 41 50 43 where Local access to the control console Use apc for the User Name and PasswordRemote access to the control console Use apc for both User Name and Password Control consoleChoose Network from the Control Console menu Web interface Quick-Start manual for access informationSnmp FTP and SCP KW InfraStruXure PDU-Operation and Configuration Customizing and Updating the PDU Important Safety InstructionsPower Cables PDU Orderable Part ListCircuit Breakers Customizing and Updating the PDU How to Add Circuit Breakers and Power Cables Add a power cable to the PDUAdd a circuit breaker on the PDU Customizing and Updating the PDU ATS 0 ATS 1 ATS Atsen How to connect contacts to the PDU monitoring unit To test your EPO wiring and switches How to Test the EPO SwitchSafety warnings Customizing and Updating the PDU How to Download Firmware Upgrades Upgrading the PDU monitor processorFrom a local computer Xmodem 60kW InfraStruXure PDU SpecificationsCompliance Product Information InfraStruXure Standard WarrantyProduct Information Life-Support Policy APC Three-Phase SystemsHow to contact APC How to Obtain ServiceAppendix Changes in This Manual General changesChanges by page number Page Index 60kW InfraStruXure PDU-Operation and Configuration Page Page Page APC Worldwide Customer Support