Revision A |
3.INSTALLATION PROCEDURES
3.1 PREPARATION
3.1.1 Recommended Tools
Tools required for installation:
•Standard selection of customary insulated hand tools used by qualified technicians.
•An appropriate drill to drill holes in the floor to anchor the plant.
•A crimping device for compressing lugs not already crimped.
3.1.2Recommended Test Equipment
Test equipment required for installation:
•Digital Multimeter
3.1.3Equipment Inspection
Remove equipment from packing material and inspect for shipping damage to verify the safety and operational suitability for the installation site. [Refer to Section 1.3.]
3.1.4 Safety Precautions
WARNING:
Hazardous energy levels are present on bare conductors in the
It is recommended that:
Any jewelry, rings or watches be removed while working on this equipment. Handles of all wrenches, screwdrivers, cutters and pliers be insulated. Shafts of screwdrivers be wrapped in electrical tape or otherwise insulated.
3.1.5 Room/Locations
NOTE: The Power Distribution Frame is to be installed in a room, vault, or similar enclosure that is accessible only to qualified persons in accordance with the NEC (National Electrical Code) or the authority having jurisdiction.
Prior to installation, drawings, floor loading requirements, and grounding schemes should all be verified. Installation drawing number