APC 10-40KW 400V UPS manual Parallel Board, Terminal Blocks X003/X004 Anxiliary Contacts

Page 19

External Connection

Terminal Blocks: X003/X004 (Anxiliary Contacts)

When switching Q001, Q002, Q010, Battery Breaker 1 or Battery Breaker 2 from “ON or 1” to “OFF or 0”, the anxiliary contact has to be open BEFORE the corresponding main contacts are opened. When switching Q001, Q002, Q010, Battery Breaker 1 or Battery Breaker 2 the opposite way from “OFF or 0” to “ON or 1”, the anxiliary contact has to close with a maximum delay of 0.5 seconds from the time the corresponding main contacts are closed.

This type of auxillary contact is called a “late make” contact. (This also means that it will “break early” when activated in opposite direction.)

This auxillary contact is also called “NORMALLY OPEN” (NO), because the auxillary contact will be open when the main contacts are open.

Please note that the above term “NORMALLY” has nothing to do with NORMAL UPS OPERATION MODE.

When switching Q003 from “OFF or 0” to “ON or 1”, the anxiliary contact has to open BEFORE the corresponding main contacts are closed. When switching Q003 the opposite way from “ON or 1” to “OFF or 0”, the auxillary contact has to close with a maximum delay of 0.5 seconds from the time when the corresponding main contacts are opened.

This type of anxiliary contact is called an “early break” contact. (This also means that it will “make late” when activated in the opposite direction.)

The auxiliary contact is also called “NORMALLY CLOSED” (NC), because the auxiliary contact will be closed when the main contacts are open.

Please note that the above term “NORMALLY” has nothing to do with NORMAL UPS OPERATION.

X005 (Output Relays)

Battery operation signals are received with a 30-second delay. This function is inactive during battery test. Common fault relay facility is programmable (standard factory setting: 10 sec.) See APC Silcon User Guide for details.

Maximum nominal voltage on contact circuits is 277VAC. If two different phases are involved, maximum phase to neutral voltage should be below 160VAC. Please note that phase L1 is already present on the System Integration Interface board, supplied from the Service Bypass Panel. Therefore, if a phase is needed for alarm or signal purposes, Phase L1 should be used.

4.3Parallel Board

CAUTION!

Control cables must be separated from AC and DC power cables.

Parallel Board

 

990-4050

 

 

Installation Guide APC Silcon 10-40kW 400V UPS

19

Image 19
Contents 10-40kW 400V UPS Installation Guide Safety Symbols used in this manual Installation Guide APC Silcon 10-40kW 400V UPSThank You Contents Appendix System SpecificationsWarranty 10.0 How to Contact APCTools IntroductionIntroduction Tools and EquipmentUnpacking UnpackingPlease Recycle 1xBP 2xBP 3xBP InstallationInstallation Requirements on SiteCabinets 1 600mm UPS Cabinet with 1xBP I or Isolation Transformer Footprint4 600mm Cabinet for 40kW UPS without Batteries 3 1000mm Cabinet for 10-20kW UPS with 3xBP5 1000mm Cabinet for 40kW UPS with 2xBP External Connection Connecting the UPSConnecting the 10-20kW UPS External ConnectionOutput Battery CableFuses 10kW 20kW Input Connecting the 40kW UPS40KW Mm2 Output CableFuses Mm2System Integration Interface Connections Parallel Board Parallel BoardTerminal Blocks X003/X004 Anxiliary Contacts X005 Output RelaysExternal Connection External Control Cables Power CablesCommunication Interface Board X50 and a serial port Connecting of APC Silcon Tripel Chassis2.1Monitoring Port Safety WarningsAPC Silcon Triple Chassis Product DescriptionIf the LED is… Then the Silcon Triple Chassis… 2.4Optional Power InputInstalling Management Peripherals 2.3LEDs3.3Daisy-chaining the APC Silcon Triple Chassis 3.2Installing Management Peripheral Cards3.1Order of Management Peripheral Cards Management Priority Position Peripheral CardManagement Peripheral Draw mA Problem Possible Cause Solution Troubleshooting5.1If Problems Persist External Connection External Connection Physical 6.2Power, Physical, and Environmental SpecificationsEnvironmental Important Safety Instructions APC Silcon Battery CabinetsPreparing Batteries External Connection External Connection External Connection Final Checks APC Silcon Battery Cabinets Diagram UPS with Battery Cabinet 5.1Installation of BatteriesSilcon Battery Breaker Box/Fuse-box 20 kW Battery Breaker BoxAmpere Connection Max Dimensions Weight Rating Cable Short Circuit Current kA 10 kWBattery Battery Breaker Box Connection DiagramFuse-box Fuse-box Connection Diagram External Connection Parameters Parameter Setting CommentsProgramming Parameters Programming ParametersProgramming Keys Programming Example Switch to Bypass Operation System ConfigurationSystem Configuration Parameters password protected Programming Example Change Charge Voltage to Change parameters by pressing Programming Parameters for Advanced Parallel Operation Description of SettingsProgramming example Battery MonitorOptions/Accessories Options/AccessoriesService Bypass Panel for Single Operation 10 x 0.75mm2 max mm2 Options/Accessories Display shows Operating The External Service Bypass SwitchLamp indication On Servive Bypass Panel 3.1Switching from External Bypass to Normal UPS OperationService Bypass Panel for Parallel Redundant Operation Two Parallel Systems with Service Bypass Panel Options/Accessories H002a Action Options/Accessories Action Lamp indication On Service Bypass PanelDisplay shows Following can be carried out on any UPS Isolating One UPS for Service/MaintenanceSwitching Back to Normal Parallel/Redundant Operation Intersystem Synchronization Unit System ISU System Intersystem Synchronization UnitIntersystem Synchronization Unit ISU Relays Relay BoardRelay Board/Relay Functions Relay Number Message Alarm-trigging EventsSee .2 in this guide for System configuration Footprint 600mm Weight EqualizerFootprint 1000mm Cabinet Extension of Remote Display Communication Distance Remote DisplayStandard Short-haul RS232 Modem Async Pin Connections for cable from host to ME800A-R2 Host 1.1Connections Without ConverterHost DTE Remote Display DTE 1.2Connections With ConverterRemote Display Cables 2.2Remote Display Power SupplyRemote Display Use 3.2Communication FaultRemote Display Setting 3.6AlarmsIsolation Transformer Height mm Width mm Depth mm Weight kgInput Fuses Input Cable Cable mm2 Output Temp FM a Connecting Isolation TransformerCable Signal Isolation External External PEOptions/Accessories Options/Accessories Options/Accessories Options/Accessories Options/Accessories Options/Accessories Back-up Time / Dimensions / Weigh System SpecificationsSystem Specifications Technical DataWarranty WarrantyAPC Silcon Series Limited Factory Warranty Appendix Installation Planning DataAppendix Appendix APC Denmark How to Contact APCHow to Contact APC APC Corporate