APC 10-40KW 400V UPS manual Final Checks

Page 37

External Connection

4.7.4 Final Checks

CAUTION!

Follow the “start-up procedure” in APC Silcon User Guide.

IMPORTANT SAFETY INSTRUCTIONS

a)The servicing of batteries requires battery knowledge and should be carried out or supervised by qualified personnel only. Keep unauthorized personnel away from batteries.

b)Use only R/C (BAZR2) batteries in UPS systems with built-in batteries. Max. battery length: 152mm

Max. battery width: 67mm

When mounting batteries allow for at least 0.2inch/0.5mm between batteries and also between batteries and battery shelf.

c)CAUTION - Batteries are fully charged on delivery. Do not short battery terminals or DC terminals.

d)CAUTION - Do not dispose of batteries in a fire. Batteries may explode.

e)CAUTION - Avoid rough treatment and opening of batteries. Released electrolyte is harmful to skin and eyes and may be toxic.

f)CAUTION - Batteries may cause electric shocks and high voltage short-circuit current. Follow the precautions below when working with batteries:

1Remove watches, rings and other metal objects.

2Use tools with insulated handles.

3Wear rubber gloves and boots.

4Do not leave tools or metal parts on top of batteries.

5Disconnect charging source prior to connecting or disconnecting batteries.

6Determine if the battery is inadvertently grounded. If inadvertently grounded, remove unwanted source of ground. Any contact with grounded battery may result in electric shocks. The likelihood of such shocks will be reduced if grounds are removed during installation and maintenance (applicable to a UPS and a remote battery supply without grounded supply circuit).

990-4050

Installation Guide APC Silcon 10-40kW 400V UPS

37

Image 37
Contents 10-40kW 400V UPS Installation Guide Safety Symbols used in this manual Installation Guide APC Silcon 10-40kW 400V UPSThank You Contents Warranty System Specifications10.0 How to Contact APC AppendixIntroduction IntroductionTools and Equipment ToolsUnpacking UnpackingPlease Recycle Installation InstallationRequirements on Site 1xBP 2xBP 3xBPCabinets 1 600mm UPS Cabinet with 1xBP I or Isolation Transformer Footprint4 600mm Cabinet for 40kW UPS without Batteries 3 1000mm Cabinet for 10-20kW UPS with 3xBP5 1000mm Cabinet for 40kW UPS with 2xBP Connecting the 10-20kW UPS Connecting the UPSExternal Connection External ConnectionOutput Battery CableFuses 10kW 20kW Input Connecting the 40kW UPSFuses Mm2 Output CableMm2 40KWSystem Integration Interface Connections Terminal Blocks X003/X004 Anxiliary Contacts Parallel BoardX005 Output Relays Parallel BoardExternal Connection External Control Cables Power CablesCommunication Interface Board X50 and a serial port Connecting of APC Silcon Tripel ChassisAPC Silcon Triple Chassis Safety WarningsProduct Description 2.1Monitoring PortInstalling Management Peripherals 2.4Optional Power Input2.3LEDs If the LED is… Then the Silcon Triple Chassis…3.1Order of Management Peripheral Cards 3.2Installing Management Peripheral CardsManagement Priority Position Peripheral Card 3.3Daisy-chaining the APC Silcon Triple ChassisManagement Peripheral Draw mA Problem Possible Cause Solution Troubleshooting5.1If Problems Persist External Connection External Connection Physical 6.2Power, Physical, and Environmental SpecificationsEnvironmental Important Safety Instructions APC Silcon Battery CabinetsPreparing Batteries External Connection External Connection External Connection Final Checks APC Silcon Battery Cabinets Diagram UPS with Battery Cabinet 5.1Installation of BatteriesSilcon Battery Breaker Box/Fuse-box Ampere Connection Max Dimensions Weight Rating Cable Short Battery Breaker BoxCircuit Current kA 10 kW 20 kWBattery Battery Breaker Box Connection DiagramFuse-box Fuse-box Connection Diagram External Connection Programming Parameters Parameter Setting CommentsProgramming Parameters ParametersProgramming Keys Programming Example Switch to Bypass Operation System ConfigurationSystem Configuration Parameters password protected Programming Example Change Charge Voltage to Change parameters by pressing Programming Parameters for Advanced Parallel Operation Description of SettingsProgramming example Battery MonitorOptions/Accessories Options/AccessoriesService Bypass Panel for Single Operation 10 x 0.75mm2 max mm2 Options/Accessories Display shows Operating The External Service Bypass SwitchLamp indication On Servive Bypass Panel 3.1Switching from External Bypass to Normal UPS OperationService Bypass Panel for Parallel Redundant Operation Two Parallel Systems with Service Bypass Panel Options/Accessories H002a Action Options/Accessories Action Lamp indication On Service Bypass PanelDisplay shows Following can be carried out on any UPS Isolating One UPS for Service/MaintenanceSwitching Back to Normal Parallel/Redundant Operation Intersystem Synchronization Unit System ISU System Intersystem Synchronization UnitIntersystem Synchronization Unit ISU Relays Relay BoardRelay Board/Relay Functions Relay Number Message Alarm-trigging EventsSee .2 in this guide for System configuration Footprint 600mm Weight EqualizerFootprint 1000mm Cabinet Extension of Remote Display Communication Distance Remote DisplayStandard Short-haul RS232 Modem Async Host DTE Remote Display DTE 1.1Connections Without Converter1.2Connections With Converter Pin Connections for cable from host to ME800A-R2 HostRemote Display Cables 2.2Remote Display Power SupplyRemote Display Setting 3.2Communication Fault3.6Alarms Remote Display UseIsolation Transformer Height mm Width mm Depth mm Weight kgCable Signal Connecting Isolation TransformerIsolation External External PE Input Fuses Input Cable Cable mm2 Output Temp FM aOptions/Accessories Options/Accessories Options/Accessories Options/Accessories Options/Accessories Options/Accessories System Specifications System SpecificationsTechnical Data Back-up Time / Dimensions / WeighWarranty WarrantyAPC Silcon Series Limited Factory Warranty Appendix Installation Planning DataAppendix Appendix How to Contact APC How to Contact APCAPC Corporate APC Denmark