| Revision B |
5.5Rectifier Installation
The APC Model MRF28H54BV rectifiers are shipped in separate containers. Follow the procedure below to install a rectifier.
1)Remove the rectifier from its shipping container.
2)Remove the rectifier retaining screw from the shelf position where the rectifier is to be installed.
3)Slide the rectifier into the shelf between the guides until it is fully seated.
4)Fasten the rectifier in place with the rectifier retaining screw.
Since all adjustments are made from the system control unit, no rectifier adjustments are necessary.
NOTE: All “FLOAT” – “BOOST/EQUALISE” switches (one is located on the front of each rectifier in the system) must be set to “FLOAT” to allow the MX28B to control the output voltage properly.
5.6 Multiple Frame Assembly
5.6.1 Power Bus Connections
Installations with multiple box frames requires splicing of the power buses. The
Splice Plates
Figure 5-5 Multi-Bay Splice Plates
18 |