IBM 3531 manual Installing the EXP300 in a rack

Page 34

ID1 - ID13,

ID2 - ID12,

ID3 - ID11,

ID4 - ID10,

ID5 - ID9,

ID6 - ID8.

7.Remove the Netfinity EXP300 from its current rack, Netbay or tower.

8.Place the Netfinity EXP300 into its new home, rack, Netbay or tower.

9.If internal switch 3 on the switch card of your Netfinity EXP300 is set on (split bus or dual bus mode), then ensure that the SCSI cable, if plugged into the left side of the Netfinity EXP300, is now plugged into the right side and vice versa. If internal switch 3 is off, you do not have to switch the SCSI cable.

10.Place the correct SCSI ID label on top of the existing SCSI ID label. See “Installing identification labels” on page 35. These labels were shipped with both the Netfinity EXP300 and with the Rack to Tower Conversion Kit.

11.Use the power on procedures in“Turning on the expansion unit” on page 3 to power your system back on.

Installing the EXP300 in a rack

The EXP300 expansion unit requires 3U (5.25 in) of Electronic Industries Association (EIA) rack-mounting space.

Important: Review the documentation that comes with your rack enclosure for safety and cabling considerations. When installing your server in a rack, the following considerations should be made:

Install the expansion unit in a maximum 35 degree C environment.

To ensure proper air flow, do not block the air vents; usually 15 cm (6 inches) of air space is sufficient.

Note: Because of the limited space in some racks, it might be easier to connect and route cables before you install the mounting brackets and hardware devices.

To ensure stability, take precautions to prevent uneven loading of the rack. Loading of the rack should begin at the bottom.

Turn off the power to your rack.

When multiple components are installed in a rack, take precautions to prevent overloading of the power outlets.

The expansion unit should always be connected to a properly grounded outlet.

Refer to the rack documentation for instructions on removing the rack enclosure doors and side panels.

Use the rack-mounting template that comes with the expansion unit to locate the rack- mounting holes and install the unit in a rack cabinet. If you do not have the template, you can use the following steps to install your expansion unit:

1.Use the following illustration of the front and rear rack mounting flanges to determine the appropriate rack-mounting holes for installing cage nuts or clip nuts to secure the Netfinity EXP300 rails. From left to right, the illustration shows the front and rear flanges respectively.

26IBM Netfinity EXP300 - Type 3531 Hardware Maintenance Manual

Image 34
Contents Ff X pypi Page Ff X pypi Page Important safety information About this manualOnline support Contents Page Features Netfinity EXP300 TypeGeneral Clustering supportDisk drive storage Problem Reference Diagnostics and Test InformationTurning on the expansion unit Turning off the expansion unit Turning off the expansion unit in an emergency Operating specificationsTurning on the expansion unit after an emergency System-management software support Symptom-to-FRU index Locations Getting started Removing CRUs Use safe practices when liftingPreparing the expansion unit StatementInternal option switches Setting the interface options and ID settingsExternal option switches Option switch 1 Power-control switchUnit ID dial switch Bridge card bay Netfinity EXP300 baysHot-swap drive bays Important information for IBM ServeRAIDHot-swap power supply/fan bays ESM and power supply baysSwitch card bay Hot-swap ESM baysFront controls, indicators, and devices Power-on LED greenRear controls, indicators, and connectors Power-supply controls, indicators, connectorsESM board user controls Working with hot-swap drives LED State Description Installing hot-swap drivesHard disk drives ServeRAID information Replacing hot-swap drives Working with hot-swap power Removing a hot-swap power supply/fan unitWorking with cards and boards Installing a hot-swap power supply / fan unitReplacing a bridge card Removing the switch card Replacing the switch cardInstalling a bridge card Removing a bridge cardReplacing an ESM board Conversion of EXP300 to a tower or from a tower Installing the EXP300 in a rack Netfinity EXP300 Type 3531 IBM Netfinity EXP300 Type 3531 Hardware Maintenance Manual Installing the EXP300 in a Tower Statement Installing identification labels Serial number label Scsi ID label Expansion unit ID label Installing the EXP300 in a NetBAY enclosure FrontRear Completing the installation Cabling the expansion unit Parts Listing System Index System Netfinity EXP300 Type FRU NoOptions Power Cords IBM Netfinity EXP300 Type 3531 Hardware Maintenance Manual Safety information General safetyElectrical safety Safety inspection guide Handling electrostatic discharge-sensitive devices Safety notices multi-lingual translations Grounding requirementsDo not Statement ≥18 kg 37 lbs ≥32 kg 70.5 lbs ≥55 kg 121.2 lbs IBM Netfinity EXP300 Type 3531 Hardware Maintenance Manual Importante PerigoPara Conectar Para Desconectar CuidadoAo levantar a máquina, faça-o com segurança Instrução IBM Netfinity EXP300 Type 3531 Hardware Maintenance Manual Related service information IBM Netfinity EXP300 Type 3531 Hardware Maintenance Manual Related service information IBM Netfinity EXP300 Type 3531 Hardware Maintenance Manual Related service information IBM Netfinity EXP300 Type 3531 Hardware Maintenance Manual Related service information IBM Netfinity EXP300 Type 3531 Hardware Maintenance Manual Related service information Connexion Déconnexion Related service information IBM Netfinity EXP300 Type 3531 Hardware Maintenance Manual Wichtig VorsichtKabel anschlieβen Kabel lösen AchtungVorsicht Achtung Pericolo Per collegare Per scollegare AttenzionePericolo Attenzione Related service information IBM Netfinity EXP300 Type 3531 Hardware Maintenance Manual Related service information Peligro Para la conexin Para la desconexiín ApágueloPeligro Precaución Send us your comments Problem determination tipsThank you for your response Trademarks IBM Page Part Number 06P8514