5.

Insert ground tube assembly (2) into cement as shown. Move assembly around to release any air

pockets in cement, then rest mounting plate on cement drainage hill. Apply some pressure to level

 

 

mounting plate on top of drainage hill. Level mounting plate and square with playing surface. Clean off

 

any excess cement on mounting plate at this time and place washers (24) on mounting bolts (19).

IMPORTANT!

NOTE ORIENTATION

Front of mounting plate (2) must be parallel with playing surface.

PLAYING SURFACE

IMPORTANT!

Check leveling of mounting plate several times with carpenter’s level while concrete is curing.

2

10

10

10

24

24

 

 

24

24

PLAYING SURFACE

IMPORTANT!: WAIT A MINIMUM OF 72 HOURS BEFORE GOING ON

TO NEXT STEP. CONCRETE MUST CURE. ALLOW ADDITIONAL TIME

FOR COLD, WET OR HUMID WEATHER.

7

08/06

ID# M88604C1

Image 7
Contents High End Residential In-Ground Basketball System Required Tools and Materials Parts List Hardware Identifier Bolts & Screws Install nuts 25 onto the ground tube bolts as shown Build drainage hill Side ViewPlaying Surface Insert bushings 19 into areas shown Mounting plate 2 as shown Playing SurfaceCompleted Assembly 08/06 ID# M88604C1 Lower yoke Attach elevator adjustment 12 toAttach elevator adjustment 12 to pole bracket First attach board 13 to upper yoke Using TWO people to hold the boardAttach backboard 13 to upper and lower Yokes 18End of the rod as shown Figure a Screws 29 into place with a phillips-head screwdriver Apply height indicator labels 32 & 31 to height indicatorsAttach height indicators Install net 4 to rim as shown08/06 ID# M88604C1 After pole has been secured to the anchor plate 2 loosen nut Feet 05 m Limited Lifetime Warranty