1.Locate Reactor A-25 on a level surface and bolt in place to the floor with 3/8 in. (10 mm) bolts, unless the Reactor needs to remain portable.

Two bolts through the 2 in. (50 mm) deep caster bushings in the rear.

Two bolts through the 3-5/8 in. (168 mm) deep caster bushings in the front.

2.Do not expose Reactor A-25 to rain.

3.If you need to move the machine, add optional wheel kit.

4.Lift with hoist only from bar spanning across top of cart.

Determine Power Source

Reactor A-25 can be wired to 3 types of power source:

230 Volt / 1 Phase

230 Volt / 3 Phase Delta (3 wire + ground PE)

380 Volt / 3 Phase WYE (4 wire + ground PE) (220 Volts to Neutral)

Improper wiring may cause electric shock or other serious injury if work is not performed properly.

Have a qualified electrician connect power and ground to main power switch terminals and ground lug.

Ensure your installation complies with all National, State, and Local safety and fire codes.

Ensure that incoming power is disconnected and locked out at the source.

NOTE: Power cord is not supplied.

3A1569B

15

Image 15
Contents Operation Contents Proportioner Heated Hose Gun Proportioner ModelsSystems Related ManualsElectric Shock Hazard Fire and Explosion Hazard Equipment Misuse Hazard Important Two-Component Material Information Changing Materials Typical Installation, without Circulation Key for FIG Typical Installation, without CirculationTypical Installation, with Circulation Typical Installation, with CirculationComponent Identification IG Typical InstallationMain Air Filter Filters system air supply Temperature Controls and Indicators See Tempera- ture Controls and IndicatorsControl Panel Size Component Main Power SwitchSetup Determine Power SourceLocate Reactor A-25 Electrical Requirements Step One Connect Electrical Cord Configure to Supply PowerWatts Heater JumpersTerminal Blocks Iso Pump Lubrication System Setup Ground System Fluid Supply ConnectionsAir Supply Connection Install Fluid Temperature Sensor FTS Recirculation / Pressure Relief LinesConnect Heated Hose Fusion AP Gun shown Initial Startup Load Fluid with Feed PumpsPressure Check Hose Manual current control mode only Set TemperaturesSupply Wet-Cups with Throat Seal Liquid Closed SprayingSB SA Spray AdjustmentsOpen Close Pressure Relief ProcedurePark ShutdownFlushing Operation Daily Start-up ProcedureOpen gun fluid manifold valves a and B Circulation Through Reactor Fluid CirculationCirculation Kit CK Part Gun Manual Circulation Through Gun ManifoldDataTrak Controls and Indicators Run ModeSetup Mode DataTrak Operation Setup ModeRun Mode See DataTrak Diagnostic CodesMaintenance Symbol Code Code Name Diagnosis Cause Diagnostic CodesTemperature Control Diagnostic Codes DataTrak Diagnostic CodesWith Wheels Without Wheels Dimension In. mm DimensionsCategory Data Technical DataGraco Information Graco Standard Warranty