Graco A-25 important safety instructions Watts, Heater Jumpers, Terminal Blocks

Page 17

Step Two - Install Power Jumpers

Find location for power jumpers which are in a plastic bag tie wrapped to the ground lug.

Heater Jumpers

Install Power Jumpers

 

ti17569a

Setup

1.Turn screws counter-clockwise on the upper part of the shroud until they stop. Pull door up and out.

2.Install red jumpers from the storage bag to the positions shown for your power.

Push the jumper firmly into the new position.

If necessary, a flat-blade screwdriver can be used under the ridge on the side of the jumper to remove them.

3.Replace front shroud.

Step Two

TB2

Terminal Blocks

Install red jumpers

380V 3ø WYE

Step Three - Reposition Heater Jumpers (if necessary)

Find location of Heater Jumpers.

Machines are shipped with heaters wired for 6000 watts. To reposition heater jumpers for 3000 watts, change jumper positions as shown below.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

230V 3ø Delta

 

 

 

230V 1ø

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.Turn screws counter-clockwise on the upper part of the shroud and remove by pulling them out.

2.Move red jumpers from the storage positions to the positions shown for your power.

A flat-blade screwdriver can be used under the ridge on the side of the jumper to remove them.

Push the jumper firmly into the new position.

3.Replace lower front shroud.

Step Three

TB2

Terminal Blocks

Position red jumpers

6000 WATTS

3000 WATTS

3A1569B

17

Image 17
Contents Operation Contents Systems Proportioner ModelsRelated Manuals Proportioner Heated Hose GunElectric Shock Hazard Fire and Explosion Hazard Equipment Misuse Hazard Important Two-Component Material Information Changing Materials Typical Installation, without Circulation Key for FIG Typical Installation, without CirculationTypical Installation, with Circulation Typical Installation, with CirculationComponent Identification IG Typical InstallationMain Air Filter Filters system air supply Control Panel Temperature Controls and IndicatorsSee Tempera- ture Controls and Indicators Size Component Main Power SwitchLocate Reactor A-25 Electrical Requirements SetupDetermine Power Source Step One Connect Electrical Cord Configure to Supply PowerTerminal Blocks WattsHeater Jumpers Air Supply Connection Iso Pump Lubrication System SetupGround System Fluid Supply Connections Connect Heated Hose Install Fluid Temperature Sensor FTSRecirculation / Pressure Relief Lines Fusion AP Gun shown Pressure Check Hose Initial StartupLoad Fluid with Feed Pumps Manual current control mode only Set TemperaturesSupply Wet-Cups with Throat Seal Liquid Closed SprayingSB SA Spray AdjustmentsPark Pressure Relief ProcedureShutdown Open CloseFlushing Operation Daily Start-up ProcedureOpen gun fluid manifold valves a and B Circulation Through Reactor Fluid CirculationCirculation Kit CK Part Gun Manual Circulation Through Gun ManifoldSetup Mode DataTrak Controls and IndicatorsRun Mode Run Mode Setup ModeSee DataTrak Diagnostic Codes DataTrak OperationMaintenance Temperature Control Diagnostic Codes Diagnostic CodesDataTrak Diagnostic Codes Symbol Code Code Name Diagnosis CauseWith Wheels Without Wheels Dimension In. mm DimensionsCategory Data Technical DataGraco Information Graco Standard Warranty
Related manuals
Manual 56 pages 23.25 Kb