Vanguard Managed Solutions MBDV41, MBDV37 installation manual Vent Opening Requirements

Page 9

OWNER’S MANUAL

VENTING INSTALLATION

Continued

3.Attach vent pipe assembly to the fire- place. Set fireplace in front of it’s perma- nent location to insure minimum clear- ances. Mark the wall for a 10" square hole (for noncombustible material such as masonry block or concrete, a 7 1/2" diam- eter hole is acceptable). See Figure 12. The center of the hole should line up with the center-line of the horizontal rigid vent pipe. Cut a 10"x10" (254mm x 254mm) square hole through combustible exterior wall (7 1/2" [190mm] diameter hole if noncombustible). Frame as necessary (see Figure 12).

Vent Opening

Combustible Wall

10"

(254mm)

10"

(254mm)

(Framing

4.Apply a bead of non-hardening mastic around the outside edge of the vent cap. Position the vent cap in the center of the 7 1/2" or 10" hole on the exterior wall with the arrow on the vent cap pointing up. Insure proper clearance of 1" to combustibles is maintained. At- tach the vent cap with four wood screws supplied (see Figure 13). Note: Re- place the wood screws with appropri- ate fasteners for stucco, brick, concrete, or other types of siding.

WARNING: Do not recess vent termination in to any wall. This will cause a fire hazard.

For vinyl siding use vinyl siding stand- offs between vent cap and exterior wall. The vinyl siding standoff prevents ex- cessive heat from melting the vinyl sid- ing material. Bolt the vent cap to the standoff. Apply non-hardening mastic around outside edge of the standoff in- stead of the vent cap assembly. Use wood screws provided to attach the standoff. See Figure 14.

5.Slide the wall thimble over the vent pipe before connecting the horizontal run to the vent cap (see Figure 15).

6.Carefully move the fireplace with vent assembly attached toward the wall and insert the vent pipe into the horizontal termination. The pipe overlap should be a minimum of 1 1/4". Apply silicone to the outer pipe connection. Fasten all vent connections with screws provided. Refer to Fireplace Installation on page 16 for instructions on securing unit to framing or floor.

7.Slide the wall thimble against the inte- rior wall surface and attach with screws provided (see Figure 15).

Cut Vinyl Siding

Away to Fit

Standoff

Wood Screw

Standoff

UP

Nut

Bolt

Apply Mastic

Vent Opening

Detail)

to All Four Sides Vent Cap

Noncombustible Wall

7 1/2" (190mm)

Figure 12 - Vent Opening Requirements

Apply Mastic to All Four Sides

UP

Wood

Screw

Vent Cap

Figure 13 - Installing Horizontal Vent Cap

Figure 14 - Installing Vinyl Siding Standoff

Interior Wall

Surface

Wall

Thimble

Vent Cap

(Horizontal

Screw

Horizontal

Termination)

 

Vent Pipe

Figure 15 - Connecting Vent Cap with Horizontal Vent Pipe

Continued

106497

9

Image 9
Contents For Your Safety OWNER’S Operation and Installation ManualCheck Local Codes Prior to Installation MBDV37 and MBDV41Safety Information Local Codes Product FeaturesGlossary Terms Product IdentificationClearances PRE-INSTALLATION PreparationLocation and Space Requirements Framing and FinishingLocation of Vent Termination PRE-INSTALLATION Preparation General VentingGeneral Venting Venting Installation Installation PrecautionsInstallation Planning Installing Vent System in a Chase Installation for Horizontal TerminationVent Opening Requirements Horizontal Venting Horizontal Termination ConfigurationsVenting with Two 90 Elbows Flat Ceiling Installation Installation for Vertical TerminationCathedral Ceiling Installation Connect a section of pipe and extend up through the holeVenting with One 90 Elbow Vertical Termination ConfigurationsVertical Venting Vertical Rigid Venting Configuration Using Two 90 ElbowsParts Lists for Venting Kits and Components High Altitude InstallationVanguard Rigid Venting Vanguard Flexible VentingElectrical Hookup for Blower Accessory Fireplace InstallationCheck GAS Type Number Description Available from Desa InternationalInstalling GA3700 Blower Blower Assembly and OperationSome Models Have Blower Assembly Preinstalled Open lower louver panel or remove for easier accessWall Switch Installation Wireless HAND-HELD Remote Control Ghrc Series InstallationInstalling Receiver Installation Items Needed Installing GAS Piping to Fireplace LocationGAS Supply Testing Connecting Fireplace to GAS SupplyInstallation Items Needed Pressure Testing Gas Supply Piping SystemClose equipment shutoff valve see Fig- ure Pressure Testing Fireplace Gas ConnectionsRemoving/Replacing Glass Door REMOVING/REPLACING Glass DoorInstalling Optional Brick Liner D8037A/D8041 Tighten all bracket screwsReplace glass door see Fireplace Models MBDV37 and MBDV41 Installing LOGS, Lava Rock and Glowing EmbersOperating Guidelines and Maintenance Instructions Manual Lighting Procedure To Appliance For Your Safety Read Before LightingOperating Fireplace Lighting To Turn OFF GASInspecting Burners Pilot AssemblyRemote Operation Operating BlowerGlass Door Cleaning and MaintenancePilot and Burners LogsMain Burner Orifice and Pilot Orifice Before YOU BeginFinal Preparation GAS Control Valve ConversionObserved Problem Possible Cause TroubleshootingParts, Trying to light the fireplacePilot’s millivoltage OrificeBurner is lit Delayed ignition burner Manifold pressure is too lowPane/LP or natural gas company Glass soots Flame impingement on logsAbove Gas leak. See Warning statementTechnical Service Replacement Parts Wiring DiagramService Hints SpecificationsMBDV37 MBDV41 Illustrated Parts BreakdownDIRECT-VENT Fireplace MBDV37 MBDV41 Parts ListWall Mount ON/OFF Switch KIT GWMS2 AccessoriesCleaning KIT GCK Brass Louver KIT106497 Warranty Information