Installation of Indoor Unit

(1)Remove the cord clamp.

(2)Process the end of the connection cords to the dimensions shown in Fig.19.

(3)Connect the end of the connection cord fully into theterminal block.

(4)Fasten the connection cord with a cord clamp.

(5)Fasten the end of the connection cord with the screw.

(6)The power cable and connecting cable are self-provided.

Fig. 19 For three phase (380-400V, 3N~, 50Hz),outdoor unit.

 

 

 

Y/G

 

INDOOR UNIT

1 2 3

 

 

TERMINAL BLOCK

 

 

OUTDOOR UNIT

R S T N 1 2 3

Y/G

TERMINAL BLOCK

POWER SUPPLY:

380-400V, 3N~,50Hz

For single phase (1PH, 220-230V~, 50Hz),outdoor unit.

INDOOR UNIT

TERMINAL BLOCK

OUTDOOR UNIT

L

N

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

TERMINAL BLOCK

 

 

 

 

 

 

 

POWER SUPPLY: 1PH,220-230V~,50Hz

1 2 3

Y/G

1 2 3 Y/G

WARNING

(1)Always use a special branch circuit and install a special receptacle to supply power to the room air conditioner.

(2)Use a circuit breaker and receptacle matched to the capacity of the room air conditioner.

(3)The circuit breaker is installed in the permanent wiring. Always use a circuit that can trip all the poles of the wiring and has an isolation distance of at least 3mm between the contacts of each pole.

(4)Perform wiring work in accordance with standards so that the room air conditioner can be operated safely and positively.

(5)Install a leakage circuit breaker in accordance with the related laws and regulations and electric company standards.

23

Image 25
Contents Operation & Installation Manual Contents Disposal of the old air conditioner ERA EAASafety Precautions Safety Precautions Automatic Operation Features and FunctionsPress the AIR Flow Direction Horizontal SET button Press the AIR Flow Direction Vertical SET buttonRIGHT/LEFT For series 282, 362, 422, 482 Name of PartsFollowing four procedures are for series 282, 362, 422, 482 Cleaning and CareOperation and Performance Heating Performance Operation TipsLocation Installation of Indoor UnitSelecting the Mounting Position Indoor Unit Supension-bolt pitch should be as shown Install the room air conditioner as followsDrilling the Holes and Attaching the Suapension Bolts For HALF-CONCESLED Installation Flat washer Installing the Coupler Heat InsulationGood Badbad Installation of Indoor Unit Electrical Wiring Electrical Requirement FRESH-AIR Intake T N 1 2 Customer Guidance Followings are not problems Trouble ShootingPoor cooling Poor cooling or heatingRemarks SeriesError display For EAA series Haier Group