Exide PAR20 manual Electrical Connections, Installing Completed Hardware Horizontal Stack

Page 14

 

 

INSTALLING

 

 

 

COMPLETED

 

 

 

 

 

 

 

 

HARDWARE

 

 

 

HORIZONTAL STACK

8.2

Figure 15

 

 

 

Figure 16

Horizontal-Multiple Stacks

8.2.1

Stacking Base Modules

It is recommended that all of the first modules with bottom supports attached (see Section 8.1.1) be placed in position first. A chalk line floor mark should be used to assure all stacks will be in a straight line. This applies for stacks end- to-end or end-to-end and back-to-back. Refer to Sections 6.5 and 8.1.3 for handling and tip over procedures.

For stacks end-to-end, module ends should be butted together so that module side channel ends meet (see Figure 17).

POSITIONING HORIZONTAL BASE MODULES

Figure 17

For stacks back-to-back, the two base modules are posi- tioned to provide a minimum 4.5” spacing between the bottoms of the modules (not I-beam edges). Refer back to Figure 1.

Refer to layout/wiring diagram for seismic shim require- ments.

8.2.2 Stack Tie Plates

At this time stack tie plates should be installed. It will be necessary to temporarily remove the hardware fastening the base modules to the I-beams.

To achieve maximum stack stability, especially where seismic conditions may exist, as well as proper interfacing of inter-stack connections, metal tie plates are provided. The plates used on stacks end to end are 3” x 1” x 1/8” with two 9/16” holes. Use one tie plate at each interface to connect the module channels of adjacent stacks. See Figure 18.

TOP MODULE

BASE MODULE

TIE PLATE ASSEMBLIES - HORIZONTAL STACKS

Figure 18

Position plates on the module channels and secure with hardware as shown. Where stacks have different heights (for example a 3 high stack adjacent to 4 high stack), install plates on shorter stack top module and adjacent module. Torque hardware to 47 Newton-meters (35 Ft-Lbs).

8.2.3 Horizontal Stacking

When all base modules are set in place, continue with stacking of subsequent modules. Procedures for assem- bly of multiple horizontal stacks are the same as outlined in section 8.1.3. Also consult layout/wiring diagram. Each stack should be built up in sequence to the same level until the top modules in all stacks are the last to be installed. The use of a line chord attached to upper mod- ule corners of opposite end modules as stacking pro- gresses aids in alignment.

This completes the mechanical assembly of the battery system.

For installation of intermodular connections and terminal plate assembly, see Section 9.

For installation of protective module cover, see Section 11.

SECTION 9: ELECTRICAL CONNECTIONS

9.0 Post Preparation

All cell posts were greased at the factory. Using either a brass bristle suede shoe brush or 3M Scotch Brite scour- ing pad, brighten the flat copper terminal surfaces to

14 ensure lowest resistance connections.

Image 14
Contents Page Table of Contents System Arrangements 13.0 13.1 13.2 13.3 13.4 13.5 13.6 13.7 14.0 14.1 15.0 15.1 Appendices List of IllustrationsList of Tables Appendix aSulfuric Acid Burns Safety MessagesGeneral Explosive GasesInstallation Considerations Delivery InformationPage Table a Unpacking Table BUnpacking Modules System AssemblySystem Arrangements Handling ModuleTIP-OVER PROCEDUREFigure- SHACKLE9 -STRAP Usage Beam Hardware Installation Beam Support InstalledTip Over Procedure Bottom Supports I-beamsTIP-OVER Procedure Module After TIP-OVER Horizontal Stacking SHACKLE-STRAP UsagePositioning Horizontal Base Modules Installing Completed Hardware Horizontal StackElectrical Connections TIE Plate Assemblies Horizontal StacksIdentification Labels Stack ConnectionsTerminal Plate Kit Materials & Assembly Description QTY PER SystemStep Protective Module CoversInitial Charge Table CModule Clear Cover Materials and Assembly Description QTY PER SystemRecommended Float Range @77F Battery OperationTemperature Correction Table D Equalizing ChargeEffects of Float Voltage Ohmic MeasurementsRecordkeeping Table ECapacity Testing Unit CleaningMaintenance TAP ConnectionsAbsolyte Battery Maintenance Report Type MANUF. Date Install Date System Voltage Battery Temperature C 100 103 104 105 106 107 108 109 110 111 112 113Bonding & Grounding of Battery Rack Appendix CPage Exide Technologies Industry Leader