7.Place a straightedge across the arbor pulley and the motor pulley. The straightedge should run across both pulleys evenly as shown in Figure 19. Adjust the motor on its mount until pulleys are aligned, then tighten all the mounting bolts.
Figure 19. Checking V-belt alignment.
8.Slip the pulley cover spacer over the pulley cover mounting bolt and fit the plastic pulley cover in place. Secure it with the wing nut provided as shown in Figure 20.
Figure 20. Attaching the pulley guard.
Wiring
G1022SM and G1022Z:
The ON/OFF switch, with attached power cord and plug, is already mounted to the saw enclo- sure. Simply connect the quick disconnect on the cord between the switch and motor.
G1022ZF, G1022ZFX and G1022PRO:
The ON/OFF switch on the ZF, ZFX and PRO models mounts directly below the front fence rail.
1.Take the
2.Now attach the switch, using two Philips¨ head screws inserted through the back of the bracket and into threaded inserts in the back side of the switch box. Tighten these so the switch box is secure.
3.Connect the quick disconnect on the cord between the switch and motor.
|
|
|
|
|
|
|
|
|
|
|
|
G1022 Series Contractor Saws |