RIDGID kt-190 manual Tool Assembly, Tool Inspection, Tool Set-Up, Installing Cables with Clamps

Page 7

Model KT-190 and KT-200 Pipe Thawing Units

Tool Assembly

WARNING

To prevent serious injury, proper assembly of the Thawing Tool is required. The following proce- dures should be followed:

Figure 3 – Thawing Tool with Cables Installed

Installing Cables with Clamps

1.Remove retaining nut from one of the lugs on back of unit.

2.Slip looped end of cable onto lug bolt with flat side to- wards unit.

3.Reinstall lug nut and secure tightly.

4.Ensure looped end of cable does not contact housing.

5.Repeat steps 1 and 2 for remaining lug.

NOTE! If cable leads are not securely fastened to thaw- ing unit, thawing time may be extended and/or unit may not function properly.

Tool Inspection

WARNING

To prevent serious injury, inspect your Pipe Thawing Tool. The following procedures should be followed.

1.Make sure Pipe Thawing Tool is unplugged and the control switches are in the OFF position.

2.Inspect the power cord and plug for damage. If the plug has been modified, is missing the grounding prong or if the cord is damaged, do not use the Thawing Tool until the cord has been replaced.

3.Inspect the cables and clamps for damage. Be sure

cable leads are securely fastened to thawing unit. If cable or clamps are damaged, do not use the Thawing Tool until they are replaced. Only use cable and clamps provided with the unit.

4.Clean any oil, grease or dirt from handles, controls and clamps.

5.Inspect the Thawing Tool for any broken or missing parts as well as damage to the metal enclosure. If any of these conditions are present, do not use the Thaw- ing Tool until any problem has been repaired.

Tool Set-Up

WARNING

To prevent serious injury, proper set-up of the tool and work area is required. The following proce- dures should be followed to set-up the Pipe Thawing Tool.

1.Check work area for:

Adequate lighting

15 Amp grounded electrical outlet

Clear path to the electrical outlet that does not contain any sources of heat or oil, sharp edges or moving parts that may damage electrical cord.

Dry place for tool and operator. Do not use the tool while standing in water.

Flammable liquids, vapors or dust that may ignite.

2.Position KT-190 or KT-200 Pipe Thawer near the area suspected of having a frozen section of pipe.

3.Make sure unit is unplugged and turned OFF. (Switch on KT-190 is in the down (OFF) position. Center switch on KT-200 is in the middle (OFF) position).

4.Uncoil both cables completely and insure they are not overlapping or in contact.

5.Follow instructions on proper placement of clamps.

WARNING Making pipe connections before plug- ging in unit prevents arcing between clamp and pipe.

NOTE! Whenever making connections, clean pipe of paint, scale rust, etc. to ensure good amperage flow from the clamps to the pipe. Poor connec- tions will cause the clamps to get much hotter than normal.

Ridge Tool Company

5

Image 7
Contents Pipe Thawing Units Table of Contents KT-190 and KT-200 Pipe Thawing Units Personal Safety General Safety InformationWork Area Safety Electrical SafetyDescription and Specifications Specific Safety InformationProblem Diagnostics Tool Set-Up Tool AssemblyInstalling Cables with Clamps Tool InspectionThawing Tap Water Lines Operating InstructionsThawing Frozen Hydronic Systems Single Zone System Tool RemovalIncreasing Thawing Capacity on KT-200 Only Special Applications ProcedureMulti-Zone System Isolating Multi-Zone SystemsParallel Operation Maintenance InstructionsTool Maintenance Tool StorageKT-200 Thawer Service and RepairElectrical Schematics KT-190 Thawer 115V/60HzDescongeladoras de tuberías KT-190 y KT-200 Índice Seguridad personal Información general de seguridadSeguridad en la zona de trabajo Seguridad eléctricaSeguridad de la Descongeladora de tuberías Información específica de seguridadUso y cuidado de la máquina ServicioDescripción y especificaciones Diagnóstico de problemasEn tuberías domiciliarias de agua potable Ensamblaje de la máquinaInstalación del cable con pinza Preparación de la máquina Inspección de la DescongeladoraDescongelación de tuberías domiciliarias de agua potable Instrucciones de funcionamientoDescongelación de redes hidrónicas congeladas Extracción de la DescongeladoraRed de zona única Cómo aislar una red multizonal Red multizonalFuncionamiento en serie Procedimiento para métodos especialesFuncionamiento en paralelo Mantenimiento de la máquina Instrucciones de mantenimientoAlmacenamiento de la máquina Servicio y reparacionesDescongeladora KT-190 115V/60Hz Esquemas eléctricosDescongeladora KT-200 Descongeladoras de tuberías KT-190 y KT-200 Ridge Tool Company