Envision Peripherals R-410A installation manual Plumbing Installation, Desuperheater Startup

Page 12

ENVISION RESIDENTIAL INSTALLATION MANUAL

Plumbing Installation

1.Inspect the dip tube in the water heater cold inlet for a check valve. If a check valve is present it must be removed or damage to the desuperheater circulator will occur.

2.Remove drain valve and fitting.

3.Thread the 3/4-inch NPT x 3-1/2-inch brass nipple into the water heater drain port.

4.Attach the center port of the 3/4-inch FPT tee to the opposite end of the brass nipple.

5.Attach the 1/2-inch copper to 3/4-inch NPT adaptor to the side of the tee closest to the unit.

6.Install the drain valve on the tee opposite the adaptor.

7.Run interconnecting tubing from the tee to DHW water out.

8.Cut the cold water “IN” line going to the water heater.

9.Insert the reducing solder tee in line with cold water “IN” line as shown.

10.Run interconnecting copper tubing between the unit DHW water “IN” and the tee (1/2-inch nominal). The recommended maximum distance is 50 feet.

11.To prevent air entrapment in the system, install a vent coupling at the highest point of the interconnecting lines.

12.Insulate all exposed surfaces of both connecting water lines with 3/8-inch wall closed cell insulation.

Note: All plumbing and piping connections must comply with local plumbing codes.

Desuperheater Startup

1.Close the drain valve to the water heater.

2.Open the cold water supply to the tank.

3.Open a hot water faucet in the building to bleed air from the system. Close when full.

4.Open the pressure relief valve to bleed any remaining air from the tank, then close.

5.If so equipped, unscrew the indicator plug 1 turn on the motor end of the pump until all air is purged from the pump, then tighten the plug. Use vent couplings to bleed air from the lines.

6.Carefully inspect all plumbing for water leaks and correct as required.

7.Before restoring electrical supply to the water heater, adjust the temperature setting on the tank.

On tanks with both upper and lower elements, the lower element should be turned down to the lowest setting, approximately 100°F. The upper element should be adjusted to 120°F to 130°F. Depending upon the specific needs of the customer, you may want to adjust the upper element differently.

On tanks with a single element, lower the thermostat setting to 120°F.

8.After the thermostat(s) is adjusted, replace the access cover and restore electrical supply to the water heater.

9.Make sure that any valves in the desuperheater water circulating circuit are open.

10.Turn on the unit to first stage heating.

11.The DHW pump should be running. When the pump is first started, open the inspection port 1 turn (if equipped) until water dribbles out, then replace. Allow the pump to run for at least five minutes to ensure that water has filled the circulator properly. Be sure the switch for the DHW pump (SW4) is “ON”. The DHW “OFF” LED on the unit should not be illuminated.

12.The temperature difference between the water entering and leaving the desuperheater should be 5°F to 15°F. The water flow should be approximately 0.4 GPM per ton of nominal cooling.

13.Allow the unit to heat water for 15 to 20 minutes to be sure operation is normal.

CAUTION: Never operate the DHW circulating pump while dry. If the unit is placed in operation before the desuperheater piping is connected, be sure that the pump switch is set to the OFF position.

12

Image 12
Contents Envision Residential Installation Manual Model Nomenclature VoltageTable of Contents General Installation Information Safety ConsiderationsInstalling Vertical Units Moving and StorageInstalling Horizontal Units Horizontal Unit MountingDuct System Water PipingWater Quality Freeze Protection Condensate DrainClosed Loop Ground Source Systems Multiple Units on One Flow CenterOpen Loop Ground Water Systems Solenoid ValveDesuperheater Connections Water Tank PreparationPlumbing Installation Desuperheater StartupUnit Power Connection Accessory RelayElectrical Connections GeneralPump Wiring Electronic ThermostatAuxiliary Heat Ratings Unit Electrical Data Single speed with ECM motorSetting Fan Speed PSC Fan Performance Data PSCPerforming this operation Setting Fan Speed ECM Fan Performance Data ECMVertical Dimensional Data Top Air DischargeHorizontal Dimensional Data TOP ViewBottomflow Left ReturnPhysical Data Single Speed Single SpeedPhysical Data Dual Capacity Dual CapacityWiring Schematics Envision Single Speed Wiring Schematic 208-230/60/1Envision Single Speed Wiring Schematic 208-230/60/1 ECM 97P774-01 6/29/06 Envision Dual Capacity Wiring Schematic 208-230/60/1- ECM Unit Power 208-230/60/197P774-02 6/29/06 Microprocessor Control ECM2 Airflow Selection DIP Switches SW1 Heat, 3rd Stage Y1,Y2,W Dual Capacity UnitsEmergency Heat W only Cooling OperationCompressor Monitoring/Comfort Alert Comfort Alert Flash CodesFault Flash Thermostat DisplaysComforTalk DIP Switch Settings Description OFF PositionBefore Powering Unit, Check The Following Unit StartupStartup Steps Operation Logic Data PSCUnit Operating Parameters Single Speed ModelsDual Capacity Models First Stage OperationPressure Drop GPMTroubleshooting LED Definitions and DiagnosticsStandard Microprocessor Controls Refrigerant SystemsPreventive Maintenance Replacement ProceduresManufactured by WFI 9000 Conservation Way Fort Wayne,