Checking the Installation
Starting the System and Observing Initial Conditions
This section describes the initial system startup processes and procedures.
To start your system, follow these steps:
Step 1 Turn on each installed power supply by turning its system power switch to the on
() position.
For
Step 2 Listen for the system blower modules or fan trays in the router; you should immediately hear them operating. In a noisy environment, place your hand in front of the exhaust vents to verify that the blower modules are operating.
Step 3 During the PRP boot process, observe the PRP alphanumeric display LEDs, which are located at one end of the PRP, near the ejector lever. (See Figure 7.)
The
|