HP Performance Optimized Data Center (POD) 40c manual Electrical power component identification

Page 11

Top view shown

Electrical power component identification

Front view shown

Item

Component

Description

 

 

 

 

 

1

Fire box*

Connection location for fire emergency and VESDAnet signals

 

2

Demarcation box*

Customer communication connection point for the following

 

 

 

components:

 

 

 

ECS

 

 

 

Security

 

 

 

Phone

 

 

 

 

 

3

415 Y/240 V 3-phase,

Feed A power for critical IT loads (electrical busways) and house power

 

 

4-wire, 800 A electrical

 

 

 

 

panel

 

 

 

 

 

 

Component identification 11

Image 11
Contents Part Number August Edition HP Performance Optimized Datacenter 40c G2 User GuidePage Contents Networking Connection portals Demarcation box Fire box Fire protection system Humidifier Controlled accessHP POD 40c G2 lighting Before you contact HP HP contact information Regulatory compliance noticesBefore you begin Operator safetyComponent safety OverviewEnvironmental considerations Fire detection and suppression Parts and part number identification Component identification Structural component identification Internal life safety components Life safety component identificationTop view shown Component Description Front view shown Component Description Electrical power component identificationInternal panel labels Component DescriptionFront view shown Electrical safety label Description HP POD 40c G2 contains a total of 20 IT racks Control cabinet component identificationHP POD 40c G2 racks Component identification EPO system Life safety systemsLife safety overview ECS touchscreen and EPO indicators EPO modes Battery backup during an EPO eventComponent Indicator color Description Fire protection systemVesda air sampling smoke detection system Fire alarm indicatorsManual fire pulls Fire system operator panel Optional Fire suppression systemFire suppression sequence of operations Emergency egressGrounding Power, electrical, and controlsPower safety Site electrical systemLightning protection Electrical and mechanical cooling capacities Power feedersFeature Specification CapacitiesElectrical panels Power distribution Electrical busway system Arc flash safetyPanel schedules Wire color codeElectrical busways Control cabinet power componentsPower, electrical, and controls Drop boxes HP POD 40c G2 lighting Power configurationsRack power Power, electrical, and controls Environmental control system overview Using the ECSEnvironmental control system Sensors Satellite control boxesTop view shown Sensor Quantity Description Facility connections to ECS Connecting to the ECSManaging the ECS from the HP POD 40c G2 Configuring the ECSEnvironmental control system Logging in remotely to the ECS Click Connect Locating the ECS IP addressesNavigating the ECS interface Password protectionIcon name Description Controller Settings screen onOverview screen Information Description Status Overview screen Basic System Configuration screenConfiguring the cold aisle temperature alarm parameters Configuring the hot aisle temperature alarm parameters Current temperature parameters appear on the related buttons Setting the dimensions of the ECS Advanced System Configuration screenEnvironmental control system Calibrating the flowmeter Enable/disable power management Controller Settings screen 40c G2 Maintenance and Service Guide or ECS alarmsAlarm Meaning Solution Safety and security alarmsFire alarm sequence of operations HP POD 40c G2 cooling system theory of operation Water supply temperatureCooling system Water quality requirements and specifications Cooling system components Side view shown Component Description FansDrains Condensation managementLeak detection Connection portals IT networking and communicationsNetworking Connection portal Connection point Quantity Diameter Demarcation boxFire box IT networking and communications Humidifier Controlled accessOptional components Standard power up procedure Power up procedureStandard HP POD 40c G2 power up procedure Standard power up checklistECS and EPO Cold weather HP POD 40c G2 power up procedureSite electrical Site chilled waterCold weather power up procedure Cold weather power up checklistPOD heating procedure Power down procedure Features Specifications SpecificationsGeneral HP POD 40c G2 specifications Electrical specificationsStandard HP POD 40c G2 racks AT978A Feature Specification Rack specificationsEnvironmental specifications Water specifications29ºC to 54ºC -20ºF to 130ºF Sample HP POD 40c G2 maintenance schedule MaintenancePeriodic maintenance HP contact information Contacting HPBefore you contact HP HP POD 40c G2 regulatory compliance Safety and NEC complianceRegulatory compliance notices Cables Regulatory compliance identification numbersFederal Communications Commission notice ModificationsRegulatory requirements for Exit signs Glossary Personal protective equipment Enclosure of sufficient size to enable entry of personnelProgrammable logic controller Uninterruptible power system Documentation feedback Index ECS, configuring ECS, logging in toWater quality 57 water temperature 56 wire color code