Install the seismic rack kit and the HP 9000 Series 800t D Class Server into an open relay rack using the following steps. References to item numbers in these steps pertain to the item numbers listed in Table 1-1 on page 10.

1.Unpack the rack-mount kit and check the hardware, using the parts list in Table 1-1 and the illustrations in this procedure to ensure that all the required parts are present.

2.Remove the standard front bezel (narrow) that was shipped installed on the computer. It is hinged at the top and secured by split molded posts which fit into openings in the metal-work. It can be removed by pulling outward at the bottom edge and lifting the top edge off the hinges.

3.Remove the emblem insert and the door from the standard bezel. These items will be transferred to the wide bezel in a later step.

The molded plastic emblem insert has three tapered split-post protrusions on the back, which insert into matching holes on the cover and spread apart when inserted to provide an interference fit. A convenient tool for compressing the split retainers is a pair of needle-nose pliers. Start at one end and push out on the emblem insert as you compress each split-post retainer from the rear.

The plastic door is pivoted in each corner on its left edge. Open the door and flex it carefully, forming a slight bow near the center on the inside edge, to pop the molded plastic pin on the bezel out of the molded socket on the bottom of the door. See Figure 1-1 on page 14.

4.To locate the position within the rack for installing the seismic rack kit, allow 5/8 in. above the top-most hole in the vertical channels needed for attaching the main bracket panels. For example, to install the kit so that the top edge of its front bezel is flush with the bottom edge of existing equipment in the rack, measure 5/8 in. below that bottom edge and note the corresponding hole in the vertical channel.

Chapter 1

13

Image 13
Contents Third Edition Addendum to D Class Enterprise ServersPage Printing History Printing HistoryAbout This Manual Contents Contents Addendum to D Class Contents Tools Needed Purpose of this AddendumSeismic Rack Kit Seismic Rack Kit Site Hazard Considerations Installation Seismic Rack Installation Installation Installation Attach cable retractor item 26, -3 to right main bracket as Tray Seismic Rack Installation Installation Connections DC Power SupplyPower supply cable is used as the main disconnect device DC Power Cable Pinouts Function Color Pin NoFor this equipment. The key switch on front of SPU does not DC Power Cable Pin Diagram Safety Grounding ProceduresReplacement Power Supply SpecificationsDC Power Specifications Data Regulatory/Safety Statements IEC Statement Worldwide FCC Statement USA OnlyInternational Acoustic Noise Emissions Product Noise Declaration Germany OnlyGeräuschemission EMC Regulatory SafetyEMC Certification EMC LabelsSafety Conforms to the following Product SpecificationsAccording to ISO/IEC Guide 22 and EN Manufacturer’s Name