Addendum to D Class Enterprise Servers System Installation Guide

Installation

Figure 1-1 Seismic Rack Installation

D Class Server

5.Attach the right and left main bracket panels (items 2, 3 in Figure 1-2 on page 15) to the vertical mounting rails of the relay rack, using hardware item 24, Table 1-1 on page 10. The bracket panel is oriented top to bottom as shown in Figure 1-2. Align the upper counter-sunk hole on the panel with the hole in the vertical channel that was noted in the previous step.

6.Attach the rear brackets (Figure 1-2, item 9, 2 places) to the right and left main brackets, using item 19 hardware in three places as shown. Attach to rear of relay rack using hardware items 16, 17, and 18 (4 pls each side).

14

Chapter 1

Image 14
Contents Addendum to D Class Enterprise Servers Third EditionPage Printing History Printing HistoryAbout This Manual Contents Contents Addendum to D Class Contents Purpose of this Addendum Tools NeededSeismic Rack Kit Seismic Rack Kit Site Hazard Considerations Installation Seismic Rack Installation Installation Installation Attach cable retractor item 26, -3 to right main bracket as Tray Seismic Rack Installation Installation DC Power Supply ConnectionsFor this equipment. The key switch on front of SPU does not DC Power Cable Pinouts Function Color Pin NoPower supply cable is used as the main disconnect device Safety Grounding Procedures DC Power Cable Pin DiagramDC Power Specifications Data SpecificationsReplacement Power Supply Regulatory/Safety Statements FCC Statement USA Only IEC Statement WorldwideInternational Geräuschemission Product Noise Declaration Germany OnlyAcoustic Noise Emissions EMC Certification SafetyEMC Regulatory EMC LabelsAccording to ISO/IEC Guide 22 and EN Conforms to the following Product SpecificationsSafety Manufacturer’s Name