8.0Install Ground Braid

8.1Select a Scotch® Mastic Strip 2230 from kit and remove white release liners. Using light tension, apply a single

wrap of mastic around the cable jacket 1/4" (6 mm) from cut edge (Figure 10). Cut off excess.

1/4" (6 mm)

Semi-Con

1ST Scotch® Mastic Strip 2230

Cable Jacket

Figure 10

8.2Position preformed ground braid with short tail over wire shield directly adjacent to cable jacket cut edge. Position long tail of ground braid, extending over cable jacket with solder block over mastic strip (Figure 11). Secure ground braid to cable jacket 4 1/2" (114 mm) from cable semi-con edge using vinyl tape (Figure 11).

NOTE: Position vinyl tape with care, it also serves as a marker for positioning the termination.

4 1/2

(114 mm)

 

Semi-Con Edge

 

Shield Wire

 

Ground Braid

 

Cable Jacket Edge

 

Solder Block

 

1ST Scotch® Mastic Strip 2230

Vinyl Tape Marker

Figure 11

78-8117-0985-2 Rev C

9

Image 9
Contents 7684-S-8 Instructions With High-K Stress ReliefKit Contents Prepare Cable Instructions For Tape Shielded CableInstall Ground Braid Special Note for Cloth or Paper SEMI-CON Insulation Shield Do not Remove Core AT this Time Install Lug or ConnectorVinyl Tape Marker Install TerminationSure to allow for depth of terminal lug Instructions for Wire Shielded Cable6 mm Constant Force Spring Trim Shield Wires This Time Counter-Clockwise Allow for depth of terminal lug Instructions for UniShield Shielded CableRemove semi-conductive jacket to dimension shown in Figure Shield Wire ND Scotch Mastic Strip Install Lug or Connector Vinyl Tape Marker Ridge at End of Cable Thru 30045 One hole Tooling IndexThru 40079 One hole Thru 40178 Two hole Conductor Size AWG & kcmil Stranded Important Notice